1829 W MICHAEL LANE 90272
Certificate Information: 1829 W MICHAEL LANE 90272
- Application / Permit
- 25010-10000-04876
- Plan Check / Job No.
- B25LA43670
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 2/6/2026
- Issuing Office
- Current Status
- Issued on 2/6/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2025 | JOE VO |
| Corrections Issued | 11/8/2025 | JOE VO |
| Quality Review Completed | 11/10/2025 | GARO TELMI |
| Plan Check Approved | 2/4/2026 | JOE VO |
| Issued | 2/6/2026 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/13/2025 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 11/13/2025 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2025 | STEVE MELGAR |
| Permit | Cleared | 11/13/2025 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 11/13/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 11/13/2025 | STEVE MELGAR |
| Low Impact Development (LID) | Cleared | 12/8/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 12/11/2025 | RUEL COLE |
| Trees in Parkway | Cleared | 12/11/2025 | MIGUEL ORNELAS |
Contact Information
| Contractor | Arttcon Inc; Lic. No.: 1138192-B | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 26227 VEVA WAY CALABASAS, CA 91302 |
Inspector Information
| MICHAEL ALLEN, (310) 914-3886 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2026 | Partial Inspection | DANIEL VERA |
| PLUMBING-Rough | 5/29/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Underground Mechanical | 5/29/2026 | Corrections Issued | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/1/2026 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 6/1/2026 | Partial Approval | MICHAEL ALLEN |