5825-5825 1/2 S INSKEEP AVE 90003

Certificate Information: 5825-5825 1/2 S INSKEEP AVE 90003

Application / Permit
25010-10000-04868
Plan Check / Job No.
B25VN28053
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] 3. NEW CONSTRUCTION OF (N) 2-STORY DETACHED ADUS (2 UNITS) PER GOVT CODE 66323(A)(4)
Permit Issued
Issued on 3/24/2026
Issuing Office
Current Status
Issued on 3/24/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/10/2025 APPLICANT
Assigned to Plan Check Engineer 10/16/2025 JOSEPH RAFOLS
Assigned to Zoning Architect 10/16/2025 NICOLE SALEEBA
Corrections Issued 10/18/2025 JOSEPH RAFOLS
Quality Review Completed 11/7/2025 HERNAN ARREOLA
Applicant returned to address corrections 1/7/2026 JOSEPH RAFOLS
Applicant returned to address corrections 3/11/2026 JOSEPH RAFOLS
Plan Check Approved 3/24/2026 JOSEPH RAFOLS
Issued 3/24/2026 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/8/2026 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 1/9/2026 CINDY QI
Sewer availability Cleared 1/9/2026 CINDY QI
Address approval Cleared 1/12/2026 DAVID LOPEZ
Roof/Waste drainage to street Cleared 1/12/2026 DAVID LOPEZ
Tenant Habitability Plan Cleared 1/12/2026 ARIC DEFUSCO
Community Plan Implem. Overlay Cleared 1/20/2026 PEDRO ZUNIGA
Community Plan Implem. Overlay Cleared 2/17/2026 SEGAL ISMAEL
Metro Rail approval Cleared 2/27/2026 JENNIFER SU
Construction near power lines Cleared 3/4/2026 RIDWAN HARDY
Zoning Plan Check Cleared 3/11/2026 NICOLE SALEEBA

Contact Information

Contractor Adu Express Construction Llc; Lic. No.: 1035634-B       ,
Contractor Arash Mofakham; Lic. No.: 1035634-B       ,
Engineer Aalam,, Yahya; Lic. No.: C94318 3111 4TH ST APT 401      SANTA MONICA, CA 90405

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2026 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/15/2026 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 5/21/2026 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/21/2026 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/2/2026 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 6/16/2026 Conditional Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 6/22/2026 Partial Approval BARRY HACHE
BUILDING-Rough-Frame 7/9/2026 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 7/9/2026 Approved ENRIQUE MIRELES
HVAC-Rough 7/9/2026 Approved ENRIQUE MIRELES
PLUMBING-Rough 7/9/2026 Approved ENRIQUE MIRELES