6136-6136 1/2 E DELPHI ST 90042
Certificate Information: 6136-6136 1/2 E DELPHI ST 90042
- Application / Permit
- 25010-10000-04749
- Plan Check / Job No.
- B25LA41757
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: New two detached one-story Accessory Dwelling Units per GCS 66323(a)(4).
- Permit Issued
- Issued on 3/31/2026
- Issuing Office
- Current Status
- Issued on 3/31/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2025 | ALEXANDER JOO |
| Assigned to Zoning Architect | 10/9/2025 | VAHE ZARUKIAN |
| Corrections Issued | 10/11/2025 | ALEXANDER JOO |
| Quality Review Completed | 10/22/2025 | ARMEN JIVALAGIAN |
| Plan Check Approved | 3/23/2026 | ALEXANDER JOO |
| Issued | 3/31/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2025 | DAVID LOPEZ |
| Trees in Parkway | Cleared | 11/26/2025 | MIGUEL ORNELAS |
| Roof/Waste drainage to street | Cleared | 12/3/2025 | DAVID LOPEZ |
| Zoning Plan Check | Cleared | 12/15/2025 | ALEXANDER JOO |
| Hydrant and Access approval | Cleared | 12/30/2025 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2026 | DAVID LOPEZ |
| Sewer availability | Cleared | 2/10/2026 | DAVID LOPEZ |
| Permit | Cleared | 3/3/2026 | DAVID LOPEZ |
| GPI Written Notices | Cleared | 3/19/2026 | ALEXANDER JOO |
| Grading Pre-Inspection | Cleared | 3/19/2026 | AL GAMBLE |
Contact Information
| Architect | David, Chong; Lic. No.: C34017 | , |
| Contractor | Owner-Builder | , |
| Engineer | Pineda,, Salvador Antonio; Lic. No.: S5233 | 560 W MAIN STREET SUITE C-328 ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/9/2026 | Approved | RONNIE MEDINA |
| PLUMBING-Rough | 5/7/2026 | Partial Approval | NICHOLAS LOPEZ |
| Sewer | 5/7/2026 | Partial Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/18/2026 | Approved | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 5/18/2026 | Approved | NICHOLAS LOPEZ |