1001 N FISKE ST 90272

Certificate Information: 1001 N FISKE ST 90272

Application / Permit
25010-10000-04584
Plan Check / Job No.
B25LA41440
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT INELIGIBLE
Permit Issued
Issued on 1/14/2026
Issuing Office
Current Status
Issued on 1/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/2/2025 APPLICANT
Assigned to Plan Check Engineer 10/8/2025 SELLA BENYAMIN
Corrections Issued 10/16/2025 SELLA BENYAMIN
Quality Review Completed 10/17/2025 HERNAN ARREOLA
Applicant returned to address corrections 12/31/2025 SELLA BENYAMIN
Plan Check Approved 1/9/2026 SERGIO SILVA
Issued 1/14/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/16/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/16/2025 BIAINA HARITUNIAN
Sewer availability Cleared 10/16/2025 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 11/7/2025 MARTIN FRAGOSO
Hydrant and Access approval Cleared 11/12/2025 JERRY KAO

Contact Information

Architect , ; Lic. No.: C34496       ,
Contractor Smith Pacific Construction Inc; Lic. No.: 1018523-B 842 RADCLIFFE AVE      PACIFIC PALISADES, CA 90272
Engineer Barajas,, George; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 3101 OCEAN PARK BLVD   STE 100, PMB 122    SANTA MONICA, CA 90405
Engineer Tucker,, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2026 Partial Inspection TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 3/11/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 3/11/2026 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 3/27/2026 Corrections Issued DANIEL VERA
Deputy Reinf. Concrete 3/31/2026 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/6/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 4/6/2026 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 4/8/2026 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/20/2026 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/20/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 4/20/2026 Approved TEMISTOCLES CAAL
PLUMBING-Rough 4/20/2026 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/29/2026 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/13/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/15/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/17/2026 Partial Approval RYAN SALAZAR