16534 W LAS CASAS PL 90272
Certificate Information: 16534 W LAS CASAS PL 90272
- Application / Permit
- 25010-10000-04471
- Plan Check / Job No.
- B25LA40751
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 2/4/2026
- Issuing Office
- Current Status
- Issued on 2/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2025 | HERNAN ARREOLA |
| Corrections Issued | 11/9/2025 | HERNAN ARREOLA |
| Quality Review Completed | 11/14/2025 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/5/2026 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/12/2026 | HERNAN ARREOLA |
| Plan Check Approved | 2/4/2026 | HERNAN ARREOLA |
| Issued | 2/4/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 11/19/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 11/19/2025 | MICHAEL BROWN |
| Low Impact Development (LID) | Cleared | 11/26/2025 | LUIS LUVANO |
| Hydrant and Access approval | Cleared | 12/1/2025 | PATRICK PEREZ |
Contact Information
| Architect | Wilken,, Richard Bea; Lic. No.: NA23086 | , |
| Contractor | Mola Builders Inc; Lic. No.: 831729-B | 3334 E COAST HWY STE 322 CORONA DEL MAR, CA 92625 |
| Engineer | Afzal,, Behzad; Lic. No.: NA79628 | , |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2026 | Not Ready for Inspection | BOBBY KEY |
| Sewer | 2/24/2026 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 3/2/2026 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 3/26/2026 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 3/26/2026 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/26/2026 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 5/13/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2026 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 6/10/2026 | Corrections Issued | MICHAEL ALLEN |
| Structural Steel Frame | 6/10/2026 | Corrections Issued | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2026 | Approved | MICHAEL ALLEN |
| Reinforced Concrete Frame | 6/16/2026 | Approved | MICHAEL ALLEN |
| Structural Steel Frame | 6/16/2026 | Approved | MICHAEL ALLEN |
| Wood Frame | 6/16/2026 | Partial Approval | MICHAEL ALLEN |
| Deputy Wood Construction | 6/17/2026 | Conditional Approval | JUAN VALENZUELA |