4451-4453 N KATHERINE AVE 91423

Certificate Information: 4451-4453 N KATHERINE AVE 91423

Application / Permit
25010-10000-04453
Plan Check / Job No.
B25LA40587
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: New 2 story SFD with attached 2 car garage and attached ADU per LAMC 12.22A.33(c) and (e). To be fully sprinklered NFPA 13D.
Permit Issued
Issued on 3/10/2026
Issuing Office
Valley
Current Status
Issued on 3/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/26/2025 APPLICANT
Assigned to Plan Check Engineer 10/2/2025 MARCELA FRANQUEZ
Assigned to Zoning Architect 10/2/2025 DAVID ZHENG
Corrections Issued 10/15/2025 MARCELA FRANQUEZ
Quality Review Completed 10/22/2025 TU HUA
Plan Check Approved 3/3/2026 MARCELA FRANQUEZ
Issued 3/10/2026 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/29/2025 PATRICK PEREZ
Address approval Cleared 10/30/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/31/2025 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 10/31/2025 ERNEST TSE
Sewer availability Cleared 10/31/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/3/2025 BIAINA HARITUNIAN
ZA Case Cleared 11/18/2025 DAVID URITA
ZI Cleared 11/18/2025 DAVID URITA
Disturb/Remove Protected Trees Cleared 2/9/2026 BRANDON WONG
Trees in Parkway Cleared 2/9/2026 BRANDON WONG
Permit Cleared 2/10/2026 JEANIE LAM
Zoning Plan Check Cleared 2/11/2026 DAVID ZHENG

Contact Information

Contractor Cali Wood Work Inc; Lic. No.: 1002653-B       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/1/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Sewer 4/1/2026 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/1/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/9/2026 Corrections Issued MISAEL ESPARZA
Deputy Steel/Welding 4/29/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/11/2026 Corrections Issued MISAEL ESPARZA
Special/Order Compliance 5/11/2026 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/20/2026 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/25/2026 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 6/25/2026 Approved MISAEL ESPARZA
Deputy Wood Construction 7/14/2026 Conditional Approval RAUL OLAGI
HVAC-Rough 7/17/2026 Corrections Issued MISAEL ESPARZA