3026 S NORTON AVE A-C 90018
Certificate Information: 3026 S NORTON AVE A-C 90018
- Application / Permit
- 25010-10000-04411
- Plan Check / Job No.
- B25LA40230
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: Convert existing 4-car garage in an (E) Duplex into an ADU per GC 66323(a)(3). Design per licensed engineer.
- Permit Issued
- Issued on 12/23/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2025 | CAROLEAN BASMA |
| Corrections Issued | 9/30/2025 | CAROLEAN BASMA |
| Applicant returned to address corrections | 11/26/2025 | CAROLEAN BASMA |
| Applicant returned to address corrections | 12/3/2025 | AMY GUEVARRA |
| Plan Check Approved | 12/17/2025 | AMY GUEVARRA |
| Issued | 12/23/2025 | APPLICANT |
| CofO in Progress | 4/27/2026 | JUSTIN HAWLEY |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 10/22/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 12/10/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: NA72538 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2026 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Drilled-In Anchors | 1/16/2026 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 1/20/2026 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 2/3/2026 | Corrections Issued | JUSTIN HAWLEY |
| Deputy Wood Construction | 2/11/2026 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 2/12/2026 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 2/12/2026 | Approved | JUSTIN HAWLEY |
| Insulation | 2/20/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 2/20/2026 | Partial Approval | GEM DE OCAMPO |
| Shower Pan | 2/20/2026 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 2/27/2026 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/27/2026 | Approved | OSVALDO PARAMO |
| Gas Test | 3/17/2026 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 4/20/2026 | Approved | JUSTIN HAWLEY |
| Final | 4/20/2026 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Rough | 4/20/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 4/27/2026 | Approved | JUSTIN HAWLEY |
| Final | 4/27/2026 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 4/27/2026 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 4/27/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 4/27/2026 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 4/27/2026 | Approved | JUSTIN HAWLEY |