3026 S NORTON AVE A-C 90018

Certificate Information: 3026 S NORTON AVE A-C 90018

Application / Permit
25010-10000-04411
Plan Check / Job No.
B25LA40230
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: Convert existing 4-car garage in an (E) Duplex into an ADU per GC 66323(a)(3). Design per licensed engineer.
Permit Issued
Issued on 12/23/2025
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2025 APPLICANT
Assigned to Plan Check Engineer 9/30/2025 CAROLEAN BASMA
Corrections Issued 9/30/2025 CAROLEAN BASMA
Applicant returned to address corrections 11/26/2025 CAROLEAN BASMA
Applicant returned to address corrections 12/3/2025 AMY GUEVARRA
Plan Check Approved 12/17/2025 AMY GUEVARRA
Issued 12/23/2025 APPLICANT
CofO in Progress 4/27/2026 JUSTIN HAWLEY
Permit Finaled 4/30/2026 DEROLD HAUFF
CofO Issued 4/30/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/22/2025 MICHAEL BROWN
Sewer availability Cleared 10/22/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 10/23/2025 MICHAEL BROWN
Construction near power lines Cleared 12/10/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274
Engineer Dorta,, Michael Rohrs; Lic. No.: NA72538       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/6/2026 Conditional Approval JUSTIN HAWLEY
Deputy Drilled-In Anchors 1/16/2026 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 1/20/2026 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 2/3/2026 Corrections Issued JUSTIN HAWLEY
Deputy Wood Construction 2/11/2026 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 2/12/2026 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 2/12/2026 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 2/12/2026 Approved JUSTIN HAWLEY
Insulation 2/20/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 2/20/2026 Partial Approval GEM DE OCAMPO
Shower Pan 2/20/2026 Approved GEM DE OCAMPO
Drywall Nailing 2/27/2026 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/27/2026 Approved OSVALDO PARAMO
Gas Test 3/17/2026 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 4/20/2026 Approved JUSTIN HAWLEY
Final 4/20/2026 Corrections Issued JUSTIN HAWLEY
Green Building Rough 4/20/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 4/20/2026 SGSOV Approved JUSTIN HAWLEY
ELECTRICAL-Final 4/27/2026 Approved JUSTIN HAWLEY
Final 4/27/2026 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 4/27/2026 Approved JUSTIN HAWLEY
HVAC-Final 4/27/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 4/27/2026 Approved JUSTIN HAWLEY
Smoke Detectors 4/27/2026 Approved JUSTIN HAWLEY