1401 W RUSTIC LANE 90272

Certificate Information: 1401 W RUSTIC LANE 90272

Application / Permit
25010-10000-04394
Plan Check / Job No.
B25LA40078
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2025 WILDFIRE NEW, DEATCHED ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE PER LAMC 12.22A.33(b)(1), 1-STORY, 75'-10.5"X26'-1". NFPA 13R SPRINKLERS THROUGHOUT EO1. SOLAR INSTALLATION EXEMPT PER GOVERNOR'S ORDER N-29-25.
Permit Issued
Issued on 3/5/2026
Issuing Office
Current Status
Issued on 3/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/26/2025 APPLICANT
Assigned to Plan Check Engineer 10/2/2025 VIVIAN LAO
Corrections Issued 10/7/2025 VIVIAN LAO
Quality Review Completed 10/7/2025 JOHN FRANCIA
Applicant returned to address corrections 1/6/2026 VIVIAN LAO
Plan Check Approved 2/24/2026 VIVIAN LAO
Issued 3/5/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/8/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/8/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/8/2025 BIAINA HARITUNIAN
Sewer availability Cleared 10/8/2025 BIAINA HARITUNIAN
Street Frontage Cleared 10/8/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 1/9/2026 RIDWAN HARDY
Watercourse Cleared 1/13/2026 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 2/6/2026 JERRY KAO
Flood clearance Cleared 2/17/2026 TUYEN LE

Contact Information

Architect Reed,, John G; Lic. No.: NA14523       ,
Contractor Sanders Construction Company; Lic. No.: 588917-B       ,
Engineer Funk,, David Lyle; Lic. No.: NA5421       ,

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/13/2026 Not Ready for Inspection HERBERT GIRON
Excavation/Setback/Form/Re-Bar 3/19/2026 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 3/19/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 3/26/2026 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 3/26/2026 Partial Approval HERBERT GIRON
FLOOD-Elevation Certificate 3/26/2026 Approved HERBERT GIRON
Footing/Foundation/Slab 3/26/2026 Partial Approval HERBERT GIRON
PLUMBING-Rough 4/2/2026 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 5/7/2026 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 5/7/2026 Approved HERBERT GIRON
Underground Mechanical 5/7/2026 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/1/2026 Corrections Issued HERBERT GIRON
PLUMBING-Rough 6/1/2026 Partial Approval HERBERT GIRON
Deputy Wood Construction 6/2/2026 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/5/2026 Partial Approval HERBERT GIRON
PLUMBING-Rough 6/5/2026 Partial Approval HERBERT GIRON
Underground Mechanical 6/5/2026 Partial Approval HERBERT GIRON