530-532 W 90TH ST 90044

Certificate Information: 530-532 W 90TH ST 90044

Application / Permit
25010-10000-04294
Plan Check / Job No.
B25LA39233
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan NEW 2-STORY DUPLEX & ATTACHED GARAGE
Permit Issued
Issued on 3/3/2026
Issuing Office
Current Status
CofO Issued on 6/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2025 APPLICANT
Assigned to Plan Check Engineer 9/18/2025 JOSEPH RAFOLS
Corrections Issued 9/20/2025 JOSEPH RAFOLS
Assigned to Zoning Architect 9/25/2025 MANUEL ZAVALETA
Quality Review Completed 10/9/2025 SINA KHOSRAVI
Plan Check Approved 1/29/2026 JOSEPH RAFOLS
Issued 3/3/2026 APPLICANT
CofO in Progress 6/26/2026 ALIZAH MAYAGOITIA
Permit Finaled 6/27/2026 DEROLD HAUFF
Permit Finaled 6/27/2026 DEROLD HAUFF
CofO Issued 6/27/2026 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 10/10/2025 EDGAR PASCUA
Hydrant and Access approval Cleared 10/16/2025 RUEL COLE
Low Impact Development (LID) Cleared 11/3/2025 ERNEST TSE
Community Plan Implem. Overlay Cleared 11/13/2025 MIGUEL ORNELAS
SB8 RUD Cleared 11/24/2025 MICHAEL ZIRBES
Address approval Cleared 12/9/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/9/2025 CINDY QI
Roof/Waste drainage to street Cleared 12/9/2025 CINDY QI
Sewer availability Cleared 12/9/2025 CINDY QI
Community Plan Implem. Overlay Cleared 12/17/2025 MANERI ROMAN
Community Plan Implem. Overlay Cleared 1/10/2026 COLLINS ALLAN
Community Plan Implem. Overlay Cleared 1/15/2026 CINDY QI
Zoning Plan Check Cleared 1/27/2026 MANUEL ZAVALETA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/17/2026 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 3/24/2026 Partial Approval BARRY HACHE
Underground Mechanical 3/24/2026 Partial Approval BARRY HACHE
Insulation 3/25/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 4/1/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Approved JOHN QUINTANILLA
HVAC-Rough 4/27/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 4/27/2026 Partial Approval SABAS ALONSO
PLUMBING-Rough 4/27/2026 Approved SABAS ALONSO
BUILDING-Rough-Frame 4/28/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 4/28/2026 Approved JOHN QUINTANILLA
Green Building Rough 4/28/2026 Approved JOHN QUINTANILLA
MERV13>=Rough 4/28/2026 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 4/28/2026 Approved JOHN QUINTANILLA
Insulation 5/1/2026 Approved JOHN QUINTANILLA
Drywall Nailing 5/7/2026 Approved RAUL BARAJAS
Interior/Exterior Lathing 5/7/2026 Approved RAUL BARAJAS
ELECTRICAL-Final 6/25/2026 Approved ALIZAH MAYAGOITIA
HVAC-Final 6/25/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 6/25/2026 Approved ALIZAH MAYAGOITIA
Final 6/26/2026 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 6/26/2026 Approved ALIZAH MAYAGOITIA
MERV13>=Final 6/26/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 6/26/2026 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/26/2026 SGSOV No Gas ALIZAH MAYAGOITIA
Service/Power Release 6/26/2026 Approved ALIZAH MAYAGOITIA
Smoke Detectors 6/26/2026 Approved ALIZAH MAYAGOITIA