567 N LAS CASAS AVE 90272
Certificate Information: 567 N LAS CASAS AVE 90272
- Application / Permit
- 25010-10000-04286
- Plan Check / Job No.
- B25LA39124
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 11/19/2025
- Issuing Office
- Current Status
- Issued on 11/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2025 | JOE VO |
| Corrections Issued | 9/27/2025 | JOE VO |
| Quality Review Completed | 9/29/2025 | GARO TELMI |
| Applicant returned to address corrections | 10/30/2025 | JOE VO |
| Plan Check Approved | 11/14/2025 | JOE VO |
| Issued | 11/19/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 11/3/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 11/3/2025 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 11/6/2025 | JERRY KAO |
| Low Impact Development (LID) | Cleared | 11/14/2025 | MARTIN FRAGOSO |
Contact Information
| Contractor | 8a General Construction; Lic. No.: 1020625-B | , |
| Engineer | Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 | 17770 CAPE JASMINE RD CANYON COUNTRY, CA 91387 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/20/2025 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 12/1/2025 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/1/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Wood Construction | 12/16/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 12/24/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 12/30/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 12/30/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 12/30/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 12/30/2025 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/30/2025 | Approved | MEL KHACHATOURIAN |
| Sewer | 12/30/2025 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 12/30/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 1/14/2026 | Corrections Issued | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Green Building Rough | 1/14/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 1/14/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 1/14/2026 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 1/15/2026 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 1/22/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 1/22/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 1/22/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/22/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Reinforced Masonry Frame | 2/2/2026 | Corrections Issued | MEL KHACHATOURIAN |
| Special/Order Compliance | 2/2/2026 | Corrections Issued | MEL KHACHATOURIAN |
| Insulation | 2/25/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/25/2026 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 3/3/2026 | Approved | MEL KHACHATOURIAN |
| Gas Test | 3/3/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/3/2026 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 4/14/2026 | Partial Approval | MEL KHACHATOURIAN |