4707 N SALOMA AVE 91403

Certificate Information: 4707 N SALOMA AVE 91403

Application / Permit
25010-10000-04282
Plan Check / Job No.
B25LA39043
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER GC 66323(A)(1)
Permit Issued
Issued on 12/3/2025
Issuing Office
Current Status
Issued on 12/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/22/2025 APPLICANT
Assigned to Plan Check Engineer 9/26/2025 SHANGQIN XIE
Corrections Issued 9/29/2025 SHANGQIN XIE
Applicant returned to address corrections 10/9/2025 TSE MING HUANG
Applicant returned to address corrections 10/29/2025 TSE MING HUANG
Plan Check Approved 11/23/2025 SHANGQIN XIE
Issued 12/3/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/8/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 10/8/2025 SAFA JAVANMARDI
Sewer availability Cleared 10/9/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 11/17/2025 SAFA JAVANMARDI
Construction near power lines Cleared 11/20/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/2/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 2/2/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/5/2026 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 2/11/2026 Corrections Issued JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/10/2026 Corrections Issued MICHAEL CORTEZ
BUILDING-Rough-Frame 4/2/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/2/2026 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/2/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/2/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/2/2026 Approved ROBERTO PALACIOS-LOPEZ
MERV13>=Rough 4/2/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/2/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 4/2/2026 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/2/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 4/3/2026 Not Ready for Inspection MICHAEL CORTEZ
Interior/Exterior Lathing 4/13/2026 Partial Approval MICHAEL CORTEZ
BUILDING-Rough-Frame 4/16/2026 Approved MICHAEL CORTEZ
Insulation 4/22/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 4/22/2026 Not Ready for Inspection MICHAEL CORTEZ
Shower Pan 4/22/2026 Approved MICHAEL CORTEZ
Drywall Nailing 4/27/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 5/4/2026 Approved MICHAEL CORTEZ