6642 W 83RD ST 90045

Certificate Information: 6642 W 83RD ST 90045

Application / Permit
25010-10000-04261
Plan Check / Job No.
B25LA38824
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan (N) 2-STORY SFD WITH ATTACHED GARAGE. TO BE EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THROUGH OUT.
Permit Issued
Issued on 12/29/2025
Issuing Office
Current Status
Issued on 12/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/15/2025 APPLICANT
Assigned to Plan Check Engineer 9/18/2025 ADRIANA LOPEZ
Assigned to Zoning Architect 9/18/2025 KAREN MEZA-MORALES
Corrections Issued 9/20/2025 ADRIANA LOPEZ
Quality Review Completed 10/6/2025 JOSE RODRIGUEZ
Applicant returned to address corrections 12/22/2025 ADRIANA LOPEZ
Plan Check Approved 12/28/2025 ADRIANA LOPEZ
Issued 12/29/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/8/2025 PATRICK PEREZ
Low Impact Development (LID) Cleared 10/9/2025 ERNEST TSE
Permit Cleared 10/14/2025 ABEL CASILLAS
Roof/Waste drainage to street Cleared 10/14/2025 ABEL CASILLAS
Sewer availability Cleared 10/15/2025 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 10/16/2025 ABEL CASILLAS
Specific Plan Cleared 10/30/2025 PEDRO AYALA
Trees in Parkway Cleared 12/4/2025 BRANDON WONG
Zoning Plan Check Cleared 12/11/2025 KAREN MEZA-MORALES

Contact Information

Contractor A P Remodeling Inc; Lic. No.: 1049032-B       ,
Contractor Ap Remodeling Inc; Lic. No.: 1049032-B       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/31/2025 Partial Approval JESUS PINEDA
Sewer 12/31/2025 Approved JESUS PINEDA
Excavation/Setback/Form/Re-Bar 1/7/2026 Approved JESUS PINEDA
Footing/Foundation/Slab 1/7/2026 Approved JESUS PINEDA
Deputy Reinf. Concrete 1/8/2026 Conditional Approval JESUS PINEDA
Sewer 1/28/2026 Approved JESUS PINEDA
Underground Mechanical 1/28/2026 Approved JESUS PINEDA
Wood Frame 2/19/2026 Partial Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Not Ready for Inspection JESUS PINEDA
Deputy Reinf. Concrete 4/3/2026 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/6/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/8/2026 Partial Approval RUBEN RIVAS
Green Building Final 4/8/2026 Not Ready for Inspection RUBEN RIVAS
Green Building Rough 4/8/2026 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 4/27/2026 Corrections Issued JESUS PINEDA
PLUMBING-Rough 4/27/2026 Approved JESUS PINEDA
ELECTRICAL-Rough 4/30/2026 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 4/30/2026 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 5/5/2026 Approved JESUS PINEDA
ELECTRICAL-Rough 5/5/2026 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 5/5/2026 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/5/2026 Off-Hour Fees Due
HVAC-Rough 5/5/2026 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 5/5/2026 Off-Hour Fees Due
Insulation 5/21/2026 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 5/21/2026 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/27/2026 Approved MICHAEL LEWIS
Green Building Rough 5/27/2026 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 5/27/2026 Approved MICHAEL LEWIS
Insulation 6/1/2026 Approved MICHAEL LEWIS
Shower Pan 6/1/2026 Approved MICHAEL LEWIS
Drywall Nailing 6/5/2026 No Result Entered MICHAEL LEWIS