4722 N WHITSETT AVE 91604
Certificate Information: 4722 N WHITSETT AVE 91604
- Application / Permit
- 25010-10000-04253
- Plan Check / Job No.
- B25LA36914
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) TWO STORY DETACHED ADU PER GC & 66323(a)(4) AT THE MIDDLE OF THE LOT.
- Permit Issued
- Issued on 4/11/2026
- Issuing Office
- Current Status
- Issued on 4/11/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2025 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 9/11/2025 | ERIC ROMERO |
| Corrections Issued | 9/15/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/30/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 2/11/2026 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/8/2026 | SERGIO GUTIERREZ |
| Issued | 4/11/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/23/2025 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/24/2025 | PATRICK PEREZ |
| Roof/Waste drainage to street | Cleared | 10/27/2025 | CARLOS AGUILERA |
| Zoning Plan Check | Cleared | 1/5/2026 | ERIC ROMERO |
Contact Information
| Contractor | Aharon R E Development Inc; Lic. No.: 1136496-B | , |
| Engineer | Gupta,, Raghu; Lic. No.: C87913 | 38725 LEXINGTON ST APT 150 FREMONT, CA 94536 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/27/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/27/2026 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 5/1/2026 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/1/2026 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 5/27/2026 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/4/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2026 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/21/2026 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 7/21/2026 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/21/2026 | Approved | CHRISTOPHE COCHRAN |