4722 N WHITSETT AVE 91604

Certificate Information: 4722 N WHITSETT AVE 91604

Application / Permit
25010-10000-04253
Plan Check / Job No.
B25LA36914
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) TWO STORY DETACHED ADU PER GC & 66323(a)(4) AT THE MIDDLE OF THE LOT.
Permit Issued
Issued on 4/11/2026
Issuing Office
Current Status
Issued on 4/11/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2025 APPLICANT
Assigned to Plan Check Engineer 9/11/2025 SERGIO GUTIERREZ
Assigned to Zoning Architect 9/11/2025 ERIC ROMERO
Corrections Issued 9/15/2025 SERGIO GUTIERREZ
Quality Review Completed 9/30/2025 PRANITA SHAH
Applicant returned to address corrections 2/11/2026 SERGIO GUTIERREZ
Plan Check Approved 4/8/2026 SERGIO GUTIERREZ
Issued 4/11/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/20/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/23/2025 CARLOS AGUILERA
Sewer availability Cleared 10/23/2025 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/24/2025 PATRICK PEREZ
Roof/Waste drainage to street Cleared 10/27/2025 CARLOS AGUILERA
Zoning Plan Check Cleared 1/5/2026 ERIC ROMERO

Contact Information

Contractor Aharon R E Development Inc; Lic. No.: 1136496-B       ,
Engineer Gupta,, Raghu; Lic. No.: C87913 38725 LEXINGTON ST APT 150      FREMONT, CA 94536

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/27/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 4/27/2026 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 5/1/2026 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/1/2026 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Wood Construction 5/27/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/4/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 6/4/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2026 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2026 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/17/2026 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/21/2026 Approved CHRISTOPHE COCHRAN
HVAC-Rough 7/21/2026 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/21/2026 Approved CHRISTOPHE COCHRAN