530 N EL MEDIO AVE 90272
Certificate Information: 530 N EL MEDIO AVE 90272
- Application / Permit
- 25010-10000-04111
- Plan Check / Job No.
- B25LA37499
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan "2025 Wildfire" NEW 2-STORY SINGLE FAMILY DWELLING AND ATTACHED 2-CAR GARAGE EO8
- Permit Issued
- Issued on 2/13/2026
- Issuing Office
- Current Status
- Issued on 2/13/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2025 | HERNAN ARREOLA |
| Corrections Issued | 9/29/2025 | HERNAN ARREOLA |
| Quality Review Completed | 10/2/2025 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 11/12/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/21/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/10/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/15/2026 | HERNAN ARREOLA |
| Plan Check Approved | 2/13/2026 | HERNAN ARREOLA |
| Issued | 2/13/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/8/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/8/2025 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 10/14/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 10/28/2025 | JERRY KAO |
| Miscellaneous | Cleared | 1/5/2026 | BRENDEN LAU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/29/2026 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/11/2026 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 5/28/2026 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2026 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2026 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Wood Construction | 7/1/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2026 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 7/20/2026 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 7/20/2026 | Approved | ARAM AVEDISIAN |