733-733 1/4 E JEFFERSON BLVD 90011

Certificate Information: 733-733 1/4 E JEFFERSON BLVD 90011

Application / Permit
25010-10000-04066
Plan Check / Job No.
B25VN24117
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW 2-STORY 2-ADU BUILDING. ADUS PER GC 66323(a)(4)
Permit Issued
Issued on 1/15/2026
Issuing Office
Current Status
Issued on 1/15/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/19/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 JESSE VIDUYA
Corrections Issued 9/4/2025 JESSE VIDUYA
Quality Review Completed 9/10/2025 CHAD DOI
Applicant returned to address corrections 11/13/2025 JESSE VIDUYA
Applicant returned to address corrections 12/19/2025 JESSE VIDUYA
Applicant returned to address corrections 1/8/2026 JESSE VIDUYA
Plan Check Approved 1/12/2026 JESSE VIDUYA
Issued 1/15/2026 APPLICANT

Permit Application Clearance Information

Historic Resource Verification Cleared 9/8/2025 RAFAEL FONTES
Address approval Cleared 9/9/2025 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 9/9/2025 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 9/9/2025 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 9/9/2025 VLADIMIR ARUTYUNYAN
Construction near power lines Cleared 1/9/2026 RIDWAN HARDY

Contact Information

Contractor Cdg Construction & Development; Lic. No.: 1148336-B       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/11/2026 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 2/17/2026 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 3/4/2026 Approved ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 3/12/2026 Conditional Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/13/2026 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 3/13/2026 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 3/17/2026 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/19/2026 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/19/2026 Approved ALEJANDRO DE ARTOLA
Deputy Wood Construction 3/26/2026 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 4/24/2026 Conditional Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/29/2026 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/5/2026 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/5/2026 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/20/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 5/20/2026 Approved ALIZAH MAYAGOITIA
Sewer 5/20/2026 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 5/27/2026 Approved BRENDAN MORELLI
Sewer 5/27/2026 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 6/2/2026 Partial Approval RAUL BARAJAS
Rough-Elec/Plmb/HVAC 6/2/2026 Partial Approval RAUL BARAJAS
Green Building Rough 6/4/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 6/4/2026 Partial Approval SABAS ALONSO
Insulation 6/11/2026 Approved ALEX COLIN
Drywall Nailing 6/16/2026 Approved LUIS CASTRO
Drywall Nailing 6/17/2026 Approved ALEX COLIN
Interior/Exterior Lathing 6/25/2026 Approved ALEX COLIN