6528 1/4-1/2 W 86TH PL 90045
Certificate Information: 6528 1/4-1/2 W 86TH PL 90045
- Application / Permit
- 25010-10000-04026
- Plan Check / Job No.
- B25LA35511
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY BUILDING AT THE REAR OF THE LOT - ONE ADU AT EACH LEVEL PER GC & 66323(a)(4). NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 3/17/2026
- Issuing Office
- Current Status
- Issued on 3/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2025 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 8/28/2025 | JASON BRAVO |
| Corrections Issued | 9/2/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/9/2025 | PRANITA SHAH |
| Plan Check Approved | 3/17/2026 | SERGIO GUTIERREZ |
| Issued | 3/17/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/10/2025 | ROSE STEIN-WENDT |
| Address approval | Cleared | 9/17/2025 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2025 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 9/19/2025 | ROSE STEIN-WENDT |
| Hydrant and Access approval | Cleared | 9/26/2025 | GILBERT URREA |
| Construction near power lines | Cleared | 10/21/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/21/2025 | RIDWAN HARDY |
| Specific Plan | Cleared | 10/24/2025 | RICHARD WOO |
| DAS Clearance | Cleared | 2/12/2026 | SERGIO GUTIERREZ |
| Zoning Plan Check | Cleared | 2/19/2026 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Lida International Building System; Lic. No.: 1064214-B | , |
| Contractor | Moo Construction; Lic. No.: 1064214-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/24/2026 | Not Ready for Inspection | MICHAEL LEWIS |
| Underground Mechanical | 6/24/2026 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 7/2/2026 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/2/2026 | Approved | EUGENE CASSIDY |