863 N FISKE ST 90272
Certificate Information: 863 N FISKE ST 90272
- Application / Permit
- 25010-10000-03996
- Plan Check / Job No.
- B25LA36578
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING, 1-STORY. NFPA 13D SPRINKLERS THROUGHOUT. INELIGIBLE
- Permit Issued
- Issued on 12/24/2025
- Issuing Office
- Current Status
- Issued on 12/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | VIVIAN LAO |
| Corrections Issued | 9/9/2025 | VIVIAN LAO |
| Quality Review Completed | 9/9/2025 | JOHN FRANCIA |
| Applicant returned to address corrections | 10/16/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 12/8/2025 | VIVIAN LAO |
| Plan Check Approved | 12/23/2025 | VIVIAN LAO |
| Issued | 12/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2025 | DERRICK MAGEE |
| Permit | Cleared | 9/9/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 9/9/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 9/9/2025 | DERRICK MAGEE |
| Construction near power lines | Cleared | 11/12/2025 | ENRIQUE ACOSTA |
| Grading Pre-Inspection | Cleared | 11/16/2025 | LANNY MERRICK |
| Hydrant and Access approval | Cleared | 12/2/2025 | KURT CORRAL |
| GPI Written Notices | Cleared | 12/23/2025 | VIVIAN LAO |
Contact Information
| Contractor | South Coast Construction & Development; Lic. No.: 1000004-B | , |
| Engineer | Masud,, Fahad Mohammed; Lic. No.: C92662 | 2415 EATON COURT ORANGE, CA 92867 |
| Engineer | Rahbar,, Farzin S; Lic. No.: S2833 | 20812 VENTURA BLVD 200 WOODLAND HILLS, CA 91364 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/12/2026 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 1/13/2026 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 1/13/2026 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2026 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/28/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2026 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2026 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 3/4/2026 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/16/2026 | Partial Approval | DANIEL VERA |
| ELECTRICAL-Rough | 4/23/2026 | Conditional Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 4/27/2026 | Corrections Issued | MICHAEL ALLEN |
| Shower Pan | 5/4/2026 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 5/21/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/29/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Green Building Rough | 5/29/2026 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 5/29/2026 | Approved | MEL KHACHATOURIAN |
| Insulation | 6/11/2026 | Approved | JESUS PINEDA |
| Drywall Nailing | 6/24/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/25/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/22/2026 | Partial Approval | ARAM AVEDISIAN |