615 N ALMA REAL DR 90272
Certificate Information: 615 N ALMA REAL DR 90272
- Application / Permit
- 25010-10000-03995
- Plan Check / Job No.
- B25LA36577
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. EO1
- Permit Issued
- Issued on 10/24/2025
- Issuing Office
- Current Status
- Issued on 10/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | JOE VO |
| Corrections Issued | 9/7/2025 | JOE VO |
| Quality Review Completed | 9/10/2025 | GARO TELMI |
| Plan Check Approved | 10/20/2025 | JOE VO |
| Issued | 10/24/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 9/8/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 9/8/2025 | DAVID LOPEZ |
| ZA Case | Cleared | 9/10/2025 | BRENNEN OBETO |
| Low Impact Development (LID) | Cleared | 9/12/2025 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 9/15/2025 | JOE VO |
| Trees in Parkway | Cleared | 9/15/2025 | RICHARD SANCHEZ |
| Hydrant and Access approval | Cleared | 9/16/2025 | KURT CORRAL |
| ZI | Cleared | 10/1/2025 | BRENNEN OBETO |
Contact Information
| Contractor | Willow Group Inc The; Lic. No.: 721043-B | 23974 CRAFTSMAN ROAD CALABASAS, CA 91302 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Kile,, Johnny C; Lic. No.: NA92658 | , |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2026 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/27/2026 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 1/30/2026 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/11/2026 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/12/2026 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/27/2026 | Approved | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 3/20/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2026 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 4/22/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Conditional Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/17/2026 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/29/2026 | Approved | STEPHANIE SWANSON |
| Insulation | 6/29/2026 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 6/30/2026 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/1/2026 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/1/2026 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/16/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/17/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| FLOOD-Proofing Certificate | 7/17/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 7/17/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 7/17/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/20/2026 | Partial Approval | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 7/20/2026 | Approved | STEPHANIE SWANSON |