12817 W DEWEY ST 90066
Certificate Information: 12817 W DEWEY ST 90066
- Application / Permit
- 25010-10000-03992
- Plan Check / Job No.
- B25LA36530
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED GARAGE TO detached ADU per state law. Work done per engineer design. **13D SPRINKLER REQUIRED, SINCE SFD REQUIRED UNDER SEPARATE PERMIT***
- Permit Issued
- Issued on 1/28/2026
- Issuing Office
- Current Status
- Issued on 1/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | KHUONG TRUONG |
| Assigned to Zoning Architect | 9/4/2025 | KRISTEL MARQUEZ |
| Corrections Issued | 9/8/2025 | KHUONG TRUONG |
| Quality Review Completed | 9/11/2025 | GARO TELMI |
| Applicant returned to address corrections | 12/3/2025 | KHUONG TRUONG |
| Applicant returned to address corrections | 12/15/2025 | KHUONG TRUONG |
| Plan Check Approved | 1/28/2026 | KHUONG TRUONG |
| Issued | 1/28/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2025 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2025 | XOCHITL ARQUIETA |
| Roof/Waste drainage to street | Cleared | 9/8/2025 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 9/8/2025 | XOCHITL ARQUIETA |
| Construction near power lines | Cleared | 10/21/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/21/2025 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 10/30/2025 | LANNY MERRICK |
| GPI Written Notices | Cleared | 12/3/2025 | KHUONG TRUONG |
| Zoning Plan Check | Cleared | 1/23/2026 | George Alvarez |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Rough | 6/9/2026 |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2026 |
| HVAC-Rough | 6/9/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2026 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 3/3/2026 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 3/11/2026 | Corrections Issued | DAKOTA LOW |
| Excavation/Setback/Form/Re-Bar | 3/16/2026 | Approved | DAKOTA LOW |
| Footing/Foundation/Slab | 3/16/2026 | Approved | DAKOTA LOW |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | Corrections Issued | DAKOTA LOW |
| Rough-Elec/Plmb/HVAC | 6/3/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Sewer | 6/3/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Underground Mechanical | 6/3/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Underground Mechanical | 6/4/2026 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/5/2026 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 6/5/2026 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 6/5/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 6/5/2026 | Approved | KIRK SANDERS |
| Underground Mechanical | 6/5/2026 | Approved | KIRK SANDERS |