4429 W AVENUE 42 90065

Certificate Information: 4429 W AVENUE 42 90065

Application / Permit
25010-10000-03968
Plan Check / Job No.
B25LA36330
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ePlan: NEW RECREATION ROOM
Permit Issued
Issued on 10/27/2025
Issuing Office
Current Status
CofO Issued on 6/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2025 APPLICANT
Assigned to Plan Check Engineer 9/3/2025 ISIS ARGUETA
Corrections Issued 9/4/2025 ISIS ARGUETA
Plan Check Approved 10/26/2025 ISIS ARGUETA
Issued 10/27/2025 APPLICANT
CofO in Progress 6/11/2026 RONNIE MEDINA
Permit Finaled 6/15/2026 DEROLD HAUFF
CofO Issued 6/15/2026 DEROLD HAUFF
Permit Finaled 6/15/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/29/2025 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 10/1/2025 JONATHAN HOM
Eng Process Fee Ord 176,300 Cleared 10/14/2025 LEE GUILBEAUX
Supp. Use District POD/CDO/TDO Cleared 10/14/2025 ANDREA MAGANA-WITHERS
ZI Cleared 10/14/2025 ANDREA MAGANA-WITHERS

Contact Information

Contractor Pacific Point Builders Inc; Lic. No.: 768984-B       ,
Engineer Grandhi,, Venkata Rohit; Lic. No.: NA88709       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/5/2025 Approved RONNIE MEDINA
Footing/Foundation/Slab 12/3/2025 Corrections Issued RONNIE MEDINA
Footing/Foundation/Slab 12/10/2025 Corrections Issued RONNIE MEDINA
Footing/Foundation/Slab 12/15/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 2/26/2026 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/26/2026 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Approved LILIANA PORTILLO
HVAC-Rough 2/26/2026 Approved LILIANA PORTILLO
MERV13>=Rough 2/26/2026 Approved LILIANA PORTILLO
PLUMBING-Rough 2/26/2026 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 2/26/2026 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/10/2026 Partial Approval RONNIE MEDINA
BUILDING-Rough-Frame 3/13/2026 Corrections Issued RONNIE MEDINA
Green Building Rough 3/13/2026 Approved RONNIE MEDINA
BUILDING-Rough-Frame 3/23/2026 Approved GEM DE OCAMPO
Insulation 3/23/2026 Approved GEM DE OCAMPO
Drywall Nailing 3/27/2026 Approved RONNIE MEDINA
ELECTRICAL-Final 5/20/2026 Corrections Issued RONNIE MEDINA
Final 5/20/2026 Corrections Issued RONNIE MEDINA
Green Building Final 5/20/2026 Approved RONNIE MEDINA
HVAC-Final 5/20/2026 Corrections Issued RONNIE MEDINA
MERV13>=Final 5/20/2026 Approved RONNIE MEDINA
PLUMBING-Final 5/20/2026 Approved RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 5/20/2026 SGSOV Approved RONNIE MEDINA
Service/Power Release 5/20/2026 Not Ready for Inspection RONNIE MEDINA
Smoke Detectors 5/20/2026 Approved RONNIE MEDINA
ELECTRICAL-Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
HVAC-Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
PLUMBING-Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
Service/Power Release 5/26/2026 Not Ready for Inspection RONNIE MEDINA
ELECTRICAL-Final 6/8/2026 Not Ready for Inspection RONNIE MEDINA
Final 6/8/2026 Not Ready for Inspection RONNIE MEDINA
HVAC-Final 6/8/2026 Not Ready for Inspection RONNIE MEDINA
PLUMBING-Final 6/8/2026 Not Ready for Inspection RONNIE MEDINA
Service/Power Release 6/8/2026 Not Ready for Inspection RONNIE MEDINA
ELECTRICAL-Final 6/10/2026 Approved RONNIE MEDINA
Final 6/10/2026 OK to Issue CofO RONNIE MEDINA
HVAC-Final 6/10/2026 Approved RONNIE MEDINA
PLUMBING-Final 6/10/2026 Approved RONNIE MEDINA
Service/Power Release 6/10/2026 Approved RONNIE MEDINA