501 N EL MEDIO AVE 90272
Certificate Information: 501 N EL MEDIO AVE 90272
- Application / Permit
- 25010-10000-03949
- Plan Check / Job No.
- B25LA36254
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO8
- Permit Issued
- Issued on 1/12/2026
- Issuing Office
- Current Status
- Issued on 1/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | STARR CHEN |
| Corrections Issued | 9/9/2025 | STARR CHEN |
| Quality Review Completed | 9/11/2025 | EUGENE BARBEAU |
| Plan Check Approved | 12/24/2025 | STARR CHEN |
| Issued | 1/12/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/15/2025 | CELINA MORENO |
| Sewer availability | Cleared | 9/15/2025 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 9/17/2025 | JERRY KAO |
Contact Information
| Contractor | Wards American Building Concepts Inc; Lic. No.: 754779-B | , |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2026 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 3/4/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 3/12/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/25/2026 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Conditional Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 4/8/2026 | Partial Approval | MEL KHACHATOURIAN |
| Pre-Inspection | 4/8/2026 | Approved | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 4/9/2026 | Conditional Approval | JUAN VALENZUELA |
| Sewer | 4/14/2026 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 6/9/2026 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2026 | Conditional Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 6/9/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 6/9/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Rough | 7/15/2026 | Corrections Issued | MEL KHACHATOURIAN |