15856 W SEABEC CIR 90272

Certificate Information: 15856 W SEABEC CIR 90272

Application / Permit
25010-10000-03923
Plan Check / Job No.
B25LA35947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND BASEMENT, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
Permit Issued
Issued on 10/29/2025
Issuing Office
Current Status
Issued on 10/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 JOE VO
Corrections Issued 9/9/2025 JOE VO
Quality Review Completed 9/12/2025 GARO TELMI
Plan Check Approved 10/23/2025 JOE VO
Issued 10/29/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/10/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 9/10/2025 MICHAEL BROWN
Sewer availability Cleared 9/10/2025 MICHAEL BROWN
Low Impact Development (LID) Cleared 9/17/2025 ERNEST TSE
Trees in Parkway Cleared 9/17/2025 RICHARD SANCHEZ
Hydrant and Access approval Cleared 9/18/2025 PATRICK PEREZ
GPI Written Notices Cleared 10/23/2025 JOE VO

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: NA53497       ,

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/6/2025 Partial Approval KENNETH NAGLE
PLUMBING-Rough 11/25/2025 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 1/15/2026 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 1/15/2026 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 1/16/2026 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 1/29/2026 Approved MEL KHACHATOURIAN
Deputy Steel/Welding 2/2/2026 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 3/10/2026 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/10/2026 Partial Approval EVAN COOPER
Deputy Steel/Welding 3/13/2026 Conditional Approval MEL KHACHATOURIAN
Deputy Steel/Welding 3/26/2026 Conditional Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 4/15/2026 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 5/12/2026 Conditional Approval JUAN VALENZUELA