530 N MUSKINGUM PL 90272

Certificate Information: 530 N MUSKINGUM PL 90272

Application / Permit
25010-10000-03855
Plan Check / Job No.
B25LA35291
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO8
Permit Issued
Issued on 12/16/2025
Issuing Office
Current Status
Issued on 12/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/5/2025 APPLICANT
Assigned to Plan Check Engineer 9/11/2025 VIVIAN LAO
Corrections Issued 9/12/2025 VIVIAN LAO
Quality Review Completed 9/12/2025 JOHN FRANCIA
Applicant returned to address corrections 10/15/2025 VIVIAN LAO
Applicant returned to address corrections 11/6/2025 VIVIAN LAO
Plan Check Approved 11/14/2025 VIVIAN LAO
Issued 12/16/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/16/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/16/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/16/2025 BIAINA HARITUNIAN
Sewer availability Cleared 9/16/2025 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 9/29/2025 RUEL COLE
Grading Pre-Inspection Cleared 10/7/2025 LANNY MERRICK
Miscellaneous Cleared 10/30/2025 KENTON TRINH
GPI Written Notices Cleared 11/14/2025 VIVIAN LAO

Contact Information

Contractor Tm Design Build; Lic. No.: 1068098-B       ,
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Geologist Van, Meter, James L.; Lic. No.: EG2031 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/19/2025 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 2/4/2026 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 3/2/2026 Order to Comply Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 3/24/2026 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 3/24/2026 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 4/17/2026 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 4/17/2026 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 4/21/2026 Partial Approval MEL KHACHATOURIAN
Deputy Reinf. Concrete 4/22/2026 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 4/30/2026 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 4/30/2026 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 5/22/2026 Conditional Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 6/5/2026 No Access for Inspection MEL KHACHATOURIAN
Wood Frame 6/5/2026 No Access for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2026 Partial Approval MEL KHACHATOURIAN