927 N LACHMAN LANE 90272
Certificate Information: 927 N LACHMAN LANE 90272
- Application / Permit
- 25010-10000-03836
- Plan Check / Job No.
- B25LA35162
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (1)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO8
- Permit Issued
- Issued on 10/17/2025
- Issuing Office
- Current Status
- Issued on 10/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2025 | JOHNNY WU |
| Corrections Issued | 9/24/2025 | JOHNNY WU |
| Quality Review Completed | 10/6/2025 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 10/16/2025 | JOHNNY WU |
| Plan Check Approved | 10/16/2025 | JOHNNY WU |
| Issued | 10/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | CINDY QI |
| Permit | Cleared | 9/25/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 9/25/2025 | CINDY QI |
| Sewer availability | Cleared | 9/25/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 9/29/2025 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 10/9/2025 | ERNEST TSE |
Contact Information
| Architect | Rene-Weissman,, Elaine M; Lic. No.: C29143 | 6624 DUME DRIVE MALIBU, CA 90265 |
| Contractor | S K Construction; Lic. No.: 633705-B | 901 CALLE SERRA SAN DIMAS, CA 91773 |
| Engineer | Bayani-Rad,, Padra; Lic. No.: C86320 | 15901 HAWTHORNE BLVD UNIT 220 LAWNDALE, CA 90260 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/17/2025 | Partial Inspection | KENNETH NAGLE |
| Underground Mechanical | 12/23/2025 | Partial Approval | DANIEL VERA |
| Deputy Drilled-In Anchors | 1/14/2026 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 1/21/2026 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/21/2026 | Conditional Approval | BOBBY KEY |
| Deputy Steel/Welding | 2/5/2026 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 2/26/2026 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/26/2026 | Approved | BOBBY KEY |
| HVAC-Rough | 3/18/2026 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 4/27/2026 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 4/27/2026 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 5/26/2026 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 5/26/2026 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 5/26/2026 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 5/26/2026 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 5/28/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 5/28/2026 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 5/29/2026 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 5/29/2026 | Corrections Issued | DANIEL VERA |
| Green Building Rough | 5/29/2026 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 5/29/2026 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 6/29/2026 | Conditional Approval | DANIEL VERA |
| Green Building Rough | 6/29/2026 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 6/29/2026 | Approved | DANIEL VERA |
| Insulation | 7/9/2026 | Conditional Approval | DANIEL VERA |