339 S AVENUE 56 90042

Certificate Information: 339 S AVENUE 56 90042

Application / Permit
25010-10000-03786
Plan Check / Job No.
B25LA34687
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: NEW 1 STORY DETACHED ACCESSORY DWELLING UNIT PER WFPP (ORDINANCE DETACHED ADU PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k))
Permit Issued
Issued on 9/19/2025
Issuing Office
Current Status
CofO Issued on 3/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2025 APPLICANT
Assigned to Plan Check Engineer 8/25/2025 DANIEL YIP
Corrections Issued 8/26/2025 DANIEL YIP
Applicant returned to address corrections 9/11/2025 DANIEL YIP
Applicant returned to address corrections 9/15/2025 AUNG SOE
Plan Check Approved 9/15/2025 AUNG SOE
Issued 9/19/2025 APPLICANT
CofO in Progress 3/27/2026 LILIANA PORTILLO
Permit Finaled 3/28/2026 DEROLD HAUFF
CofO Issued 3/28/2026 DEROLD HAUFF
Permit Finaled 3/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/3/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/3/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 9/3/2025 JEANIE LAM
Sewer availability Cleared 9/3/2025 JEANIE LAM
Grading Pre-Inspection Cleared 9/5/2025 CHARLES POWELL
GPI Written Notices Cleared 9/11/2025 DANIEL YIP

Contact Information

Contractor H I C Builders Inc; Lic. No.: 1078180-B       ,
Contractor Hic Builders Inc; Lic. No.: 1078180-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/10/2025 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 10/10/2025 Corrections Issued LILIANA PORTILLO
Sewer 10/10/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 10/16/2025 Partial Approval LILIANA PORTILLO
Pre-Inspection 10/21/2025 Partial Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 10/29/2025 Corrections Issued LILIANA PORTILLO
Underground Mechanical 10/29/2025 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 11/3/2025 Approved LILIANA PORTILLO
Footing/Foundation/Slab 11/3/2025 Approved LILIANA PORTILLO
ELECTRICAL-Rough 12/12/2025 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 12/12/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 12/12/2025 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 12/12/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 12/17/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/22/2025 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 12/22/2025 Approved LILIANA PORTILLO
HVAC-Rough 12/22/2025 Approved LILIANA PORTILLO
Shower Pan 12/23/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 12/30/2025 Approved DAVID WILLIAMS
Green Building Rough 12/30/2025 Approved DAVID WILLIAMS
Insulation 12/30/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 12/30/2025 Approved DAVID WILLIAMS
MERV13>=Rough 12/30/2025 Approved DAVID WILLIAMS
Drywall Nailing 1/5/2026 Approved ALIZAH MAYAGOITIA
Underground Mechanical 1/9/2026 Approved LILIANA PORTILLO
Underground Mechanical 1/13/2026 Approved ALIZAH MAYAGOITIA
Final 3/16/2026 Corrections Issued LILIANA PORTILLO
Green Building Final 3/16/2026 Not Ready for Inspection LILIANA PORTILLO
MERV13>=Final 3/16/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 3/16/2026 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 3/16/2026 Approved LILIANA PORTILLO
Final 3/23/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 3/23/2026 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/23/2026 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 3/23/2026 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 3/26/2026 Approved LILIANA PORTILLO
Final 3/26/2026 OK to Issue CofO LILIANA PORTILLO
Green Building Final 3/26/2026 Approved LILIANA PORTILLO
HVAC-Final 3/26/2026 Approved LILIANA PORTILLO
PLUMBING-Final 3/26/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Approved LILIANA PORTILLO
Service/Power Release 3/26/2026 Approved LILIANA PORTILLO