1455 1/4-1/2 W 28TH ST 90007
Certificate Information: 1455 1/4-1/2 W 28TH ST 90007
- Application / Permit
- 25010-10000-03760
- Plan Check / Job No.
- B25LA34431
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 2-story two detached Accessory Dwelling Units per GCS 66323(a)(2)
- Permit Issued
- Issued on 2/2/2026
- Issuing Office
- Current Status
- Issued on 2/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | ALEXANDER JOO |
| Corrections Issued | 9/10/2025 | ALEXANDER JOO |
| Quality Review Completed | 9/17/2025 | GARO TELMI |
| Applicant returned to address corrections | 10/2/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 11/4/2025 | ALEXANDER JOO |
| Plan Check Approved | 1/20/2026 | ALEXANDER JOO |
| Issued | 2/2/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2025 | CELINA MORENO |
| Sewer availability | Cleared | 10/8/2025 | CELINA MORENO |
| Address approval | Cleared | 10/28/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 10/28/2025 | CELINA MORENO |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | , |
| Engineer | Xia,, Ji; Lic. No.: S7144 | 260 S LOS ROBLES AVE, STE 100 PASADENA, CA 91101 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/27/2026 | Partial Approval | WILLIAM SIERRA |
| Footing/Foundation/Slab | 4/29/2026 | Partial Approval | WILLIAM SIERRA |
| METHANE-Barrier | 4/29/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Subgrade | 4/29/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Footing/Foundation/Slab | 5/7/2026 | Approved | WILLIAM SIERRA |
| METHANE-Barrier | 5/7/2026 | Approved | WILLIAM SIERRA |
| METHANE-Subgrade | 5/7/2026 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2026 | Partial Approval | WILLIAM SIERRA |