132 S CLARENCE ST 90033

Certificate Information: 132 S CLARENCE ST 90033

Application / Permit
25010-10000-03742
Plan Check / Job No.
B25LA34381
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
Eplan. New detached carport. Per engineering design.
Permit Issued
Issued on 11/20/2025
Issuing Office
Current Status
Issued on 11/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/19/2025 APPLICANT
Assigned to Plan Check Engineer 8/20/2025 ALFREDO JARA
Corrections Issued 8/21/2025 ALFREDO JARA
Applicant returned to address corrections 10/14/2025 ALFREDO JARA
Applicant returned to address corrections 10/30/2025 ALFREDO JARA
Plan Check Approved 11/9/2025 ALFREDO JARA
Issued 11/20/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/4/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 11/4/2025 DAVID LOPEZ
ZI Cleared 11/5/2025 GEORGIA SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Phan,, Phillip Trung Tri; Lic. No.: C76425 641 S ALMIRANTE DR      WEST COVINA, CA 91791

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/10/2026 Not Ready for Inspection PEDRO SIERRA
Footing/Foundation/Slab 2/10/2026 Not Ready for Inspection PEDRO SIERRA
Footing/Foundation/Slab 2/24/2026 Approved PEDRO SIERRA
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Partial Approval PEDRO SIERRA
Wood Frame 3/5/2026 Partial Approval PEDRO SIERRA
Drywall Nailing 3/9/2026 Approved DANIEL DELACRUZ
Interior/Exterior Lathing 3/12/2026 Approved PEDRO SIERRA
Final 4/1/2026 Not Ready for Inspection DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Approved DANIEL DELACRUZ
Smoke Detectors 4/1/2026 No Access for Inspection DANIEL DELACRUZ
Wood Frame 4/1/2026 Approved DANIEL DELACRUZ
Final 4/3/2026 Not Ready for Inspection DANIEL DELACRUZ
Smoke Detectors 4/3/2026 Not Ready for Inspection DANIEL DELACRUZ
Final 4/6/2026 Partial Approval DANIEL DELACRUZ
Smoke Detectors 4/6/2026 Approved DANIEL DELACRUZ