15461 W ALBRIGHT ST - 90272
Certificate Information: 15461 W ALBRIGHT ST - 90272
- Application / Permit
- 25010-10000-03733
- Plan Check / Job No.
- B25LA34287
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Current Status
- Issued on 11/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | JOE VO |
| Corrections Issued | 8/26/2025 | JOE VO |
| Quality Review Completed | 8/29/2025 | GARO TELMI |
| Plan Check Approved | 10/23/2025 | JOE VO |
| Issued | 11/3/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 8/26/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 8/26/2025 | ABEL CASILLAS |
| Low Impact Development (LID) | Cleared | 9/12/2025 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 9/24/2025 | PATRICK PEREZ |
| GPI Written Notices | Cleared | 10/14/2025 | JOE VO |
Contact Information
| Architect | Weaver,, Daniel R; Lic. No.: NA25502 | , |
| Contractor | Owner-Builder | , |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: NA49104 | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2025 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 2/2/2026 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/2/2026 | Partial Approval | TEMISTOCLES CAAL |
| Grounding or Bonding | 2/2/2026 | Approved | TEMISTOCLES CAAL |
| Reinforced Concrete Frame | 3/11/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Shotcrete | 3/16/2026 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 3/25/2026 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 4/1/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 4/14/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 5/1/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Steel/Welding | 5/5/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 5/26/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2026 | Conditional Approval | TEMISTOCLES CAAL |
| Structural Steel Frame | 6/16/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2026 | Corrections Issued | JUAN VALENZUELA |