16780 W BOLLINGER DR 90272
Certificate Information: 16780 W BOLLINGER DR 90272
- Application / Permit
- 25010-10000-03719
- Plan Check / Job No.
- B25LA34206
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/11/2025
- Issuing Office
- Current Status
- Issued on 12/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2025 | JOE VO |
| Corrections Issued | 9/25/2025 | JOE VO |
| Quality Review Completed | 9/29/2025 | GARO TELMI |
| Applicant returned to address corrections | 11/20/2025 | JOE VO |
| Plan Check Approved | 12/9/2025 | JOE VO |
| Issued | 12/11/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 9/29/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/29/2025 | MICHAEL BROWN |
| Trees in Parkway | Cleared | 10/3/2025 | RICHARD SANCHEZ |
| GPI Written Notices | Cleared | 12/1/2025 | JOE VO |
| Hydrant and Access approval | Cleared | 12/8/2025 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 12/8/2025 | ERNEST TSE |
Contact Information
| Contractor | Watt Palisades; Lic. No.: 694749-B | , |
| Engineer | Nikjoo,, Shahram; Lic. No.: C36969 | 6011 E BRIGHTON LANE ANAHEIM, CA 92807 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| HVAC-Rough | 6/8/2026 |
Inspection Request History
| Pre-Inspection | 1/6/2026 | Partial Inspection | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 3/4/2026 | Partial Approval | BOBBY KEY |
| Deputy Other (see comments) | 3/6/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 3/6/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 3/19/2026 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 3/24/2026 | Approved | BOBBY KEY |
| Deputy Steel/Welding | 4/8/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2026 | Partial Approval | DANIEL VERA |