1558 1/2 W 214TH ST 90501

Certificate Information: 1558 1/2 W 214TH ST 90501

Application / Permit
25010-10000-03695
Plan Check / Job No.
B25LA34036
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN PROPOSED TWO STORY ACCESSORY DWELLING UNIT PER ORDINANCE WITH ATTACHED GARAGE.
Permit Issued
Issued on 1/16/2026
Issuing Office
Current Status
Issued on 1/16/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/18/2025 APPLICANT
Assigned to Plan Check Engineer 8/21/2025 MICHAEL LOPEZ
Corrections Issued 9/3/2025 MICHAEL LOPEZ
Quality Review Completed 9/16/2025 MICHAEL PEREZ
Applicant returned to address corrections 10/7/2025 MICHAEL LOPEZ
Applicant returned to address corrections 12/2/2025 MICHAEL LOPEZ
Plan Check Approved 12/10/2025 MICHAEL LOPEZ
Issued 1/16/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/6/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 9/6/2025 DAVID LOPEZ
Hydrant and Access approval Cleared 9/9/2025 FRANK GOMEZ
Eng Process Fee Ord 176,300 Cleared 9/29/2025 DAVID LOPEZ
Sewer availability Cleared 9/29/2025 DAVID LOPEZ

Contact Information

Contractor Paramount Construction Inc; Lic. No.: 1080565-B 11801 GARFIELD AVE      SOUTH GATE, CA 90280
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/6/2026 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 3/6/2026 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/10/2026 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/13/2026 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/1/2026 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 4/1/2026 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 4/1/2026 Approved EUGENE CASSIDY
Green Building Rough 4/1/2026 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 4/1/2026 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 4/1/2026 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 4/21/2026 Approved EUGENE CASSIDY
Sewer 4/21/2026 Approved EUGENE CASSIDY
Wood Frame 4/21/2026 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 5/1/2026 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/11/2026 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 5/11/2026 Corrections Issued BEN MOLSTAD
Insulation 5/13/2026 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 5/13/2026 Partial Approval EUGENE CASSIDY
Wood Frame 5/13/2026 Approved EUGENE CASSIDY
Insulation 5/15/2026 Approved EUGENE CASSIDY
Drywall Nailing 5/22/2026 Approved EUGENE CASSIDY
Shower Pan 5/22/2026 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 5/27/2026 Approved EUGENE CASSIDY
Shower Pan 5/27/2026 Approved EUGENE CASSIDY