1243 1/2 W 41ST PL 90037

Certificate Information: 1243 1/2 W 41ST PL 90037

Application / Permit
25010-10000-03676
Plan Check / Job No.
B25LA33774
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1 STORY DETACHED ADU WITH PORCH PER CITY ORDINANCE. WORK PER ENGR DESIGN.
Permit Issued
Issued on 3/6/2026
Issuing Office
Valley
Current Status
Issued on 3/6/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2025 APPLICANT
Assigned to Plan Check Engineer 8/19/2025 FERNANDO FLORES
Corrections Issued 8/20/2025 FERNANDO FLORES
Building Plans Picked Up 8/22/2025 APPLICANT
Applicant returned to address corrections 12/9/2025 SUNMIN LEE
Applicant returned to address corrections 1/5/2026 NGHI SU
Plan Check Approved 2/26/2026 DANIEL YIP
Issued 3/6/2026 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/15/2025 RIDWAN HARDY
ZA Case Cleared 11/4/2025 BRENNEN OBETO
Address approval Cleared 12/4/2025 CINDY QI
Roof/Waste drainage to street Cleared 12/4/2025 CINDY QI
Sewer availability Cleared 12/4/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/5/2026 CINDY QI
Community Plan Implem. Overlay Cleared 2/25/2026 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/1/2026 Partial Approval SABAS ALONSO
Underground Mechanical 4/1/2026 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/6/2026 Approved SABAS ALONSO
ELECTRICAL-Rough 4/28/2026 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/28/2026 Approved SABAS ALONSO
HVAC-Rough 4/28/2026 Approved SABAS ALONSO
PLUMBING-Rough 4/28/2026 Approved SABAS ALONSO
Green Building Rough 4/30/2026 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/1/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 5/1/2026 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 5/4/2026 No Access for Inspection SABAS ALONSO
Insulation 5/5/2026 Approved SABAS ALONSO
Drywall Nailing 5/11/2026 No Access for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/11/2026 No Access for Inspection SABAS ALONSO
Drywall Nailing 5/12/2026 Corrections Issued SABAS ALONSO
Drywall Nailing 5/14/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 5/14/2026 Approved SABAS ALONSO
Shower Pan 5/18/2026 No Access for Inspection ALEX COLIN
Shower Pan 5/20/2026 Approved ALEX COLIN
Sewer 6/23/2026 Approved SABAS ALONSO
Underground Mechanical 6/23/2026 Approved SABAS ALONSO
Final 6/29/2026 Corrections Issued SABAS ALONSO
Final 6/30/2026 Corrections Issued SABAS ALONSO
Green Building Final 6/30/2026 Approved SABAS ALONSO
PLUMBING-Final 6/30/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/30/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 6/30/2026 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 6/30/2026 Approved SABAS ALONSO