341 N BEIRUT AVE 90272
Certificate Information: 341 N BEIRUT AVE 90272
- Application / Permit
- 25010-10000-03664
- Plan Check / Job No.
- B25LA33575
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE. NFPA 13D SPRINKLERS THROUGHOUT EO8
- Permit Issued
- Issued on 12/8/2025
- Issuing Office
- Current Status
- Issued on 12/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | HERNAN ARREOLA |
| Corrections Issued | 8/25/2025 | HERNAN ARREOLA |
| Quality Review Completed | 8/27/2025 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 11/26/2025 | HERNAN ARREOLA |
| Issued | 12/8/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/16/2025 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 10/3/2025 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 10/6/2025 | JOHN CONNEALLY |
Contact Information
| Architect | Cung,, Thiep Hoang; Lic. No.: C18995 | 2810 E VALLEY ROAD SANTA BARBARA, CA 93108 |
| Contractor | Western Built Construction Inc; Lic. No.: 951783-B | , |
| Engineer | Wolfe,, Justin; Lic. No.: C63735 | 1567 ROYAL WAY SAN LUIS OBISPO, CA 93405 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2025 | Partial Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/3/2026 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/5/2026 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 2/7/2026 | Corrections Issued | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 2/9/2026 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/23/2026 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2026 | Not Ready for Inspection | DANIEL VERA |
| Wood Frame | 3/6/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Steel/Welding | 4/1/2026 | Conditional Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/6/2026 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 4/13/2026 | Not Ready for Inspection | STEPHANIE SWANSON |
| Deputy Wood Construction | 4/17/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2026 | Partial Approval | MICHAEL ALLEN |
| Deputy Wood Construction | 5/8/2026 | Conditional Approval | DAVID FEILER |
| PLUMBING-Rough | 5/13/2026 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2026 | Approved | HERBERT GIRON |
| Sewer | 6/5/2026 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 6/5/2026 | Approved | STEPHANIE SWANSON |