2029 S GLYNDON AVE 90291
Certificate Information: 2029 S GLYNDON AVE 90291
- Application / Permit
- 25010-10000-03621
- Plan Check / Job No.
- B25LA31992
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2 Car Garage and ADU per LAMC 12.22A.33(b)(1)
- Permit Issued
- Issued on 12/8/2025
- Issuing Office
- Current Status
- Issued on 12/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 8/7/2025 | SARHAD GHEVANDIAN |
| Corrections Issued | 8/11/2025 | HERNAN ARREOLA |
| Quality Review Completed | 8/18/2025 | GARO TELMI |
| Applicant returned to address corrections | 9/26/2025 | HERNAN ARREOLA |
| Plan Check Approved | 10/6/2025 | HERNAN ARREOLA |
| Issued | 12/8/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/25/2025 | RIDWAN HARDY |
| Address approval | Cleared | 8/31/2025 | CHRISTINE REUSCH |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2025 | CHRISTINE REUSCH |
| Roof/Waste drainage to street | Cleared | 8/31/2025 | CHRISTINE REUSCH |
| Sewer availability | Cleared | 8/31/2025 | CHRISTINE REUSCH |
| Specific Plan | Cleared | 9/15/2025 | PEDRO AYALA |
| Zoning Plan Check | Cleared | 9/18/2025 | SARHAD GHEVANDIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Irene; Lic. No.: NA68382 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 1/12/2026 | Approved | RUBEN RIVAS |
| ELECTRICAL-Rough | 1/28/2026 | Approved | RUBEN RIVAS |
| HVAC-Rough | 1/28/2026 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2026 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/2/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2026 | Approved | MICHAEL ALLEN |
| Green Building Rough | 3/2/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 3/2/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 3/4/2026 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/9/2026 | Approved | RUBEN RIVAS |
| Green Building Rough | 3/9/2026 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/9/2026 | Partial Approval | RUBEN RIVAS |
| Shower Pan | 3/9/2026 | Approved | RUBEN RIVAS |
| Insulation | 3/13/2026 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/18/2026 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 3/23/2026 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 7/10/2026 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 7/10/2026 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/16/2026 | Approved | RUBEN RIVAS |
| HVAC-Final | 7/16/2026 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Final | 7/16/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 7/20/2026 | Approved | RUBEN RIVAS |