4422 S GRAND VIEW BLVD 90066
Certificate Information: 4422 S GRAND VIEW BLVD 90066
- Application / Permit
- 25010-10000-03539
- Plan Check / Job No.
- B25LA32489
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Construction of a new 1-story detached ADU per GC 66323(a)(2) state code
- Permit Issued
- Issued on 11/22/2025
- Issuing Office
- Current Status
- Issued on 11/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | PRANITA SHAH |
| Corrections Issued | 8/18/2025 | PRANITA SHAH |
| Quality Review Completed | 8/20/2025 | GARO TELMI |
| Assigned to Zoning Architect | 8/21/2025 | ELAHE MERRIKHI |
| Applicant returned to address corrections | 9/30/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 11/4/2025 | PRANITA SHAH |
| Plan Check Approved | 11/19/2025 | PRANITA SHAH |
| Issued | 11/22/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2025 | WALLIE JONG |
| Construction near power lines | Cleared | 9/2/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2025 | WALLIE JONG |
| Sewer availability | Cleared | 9/2/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/5/2025 | WALLIE JONG |
| Specific Plan | Cleared | 11/5/2025 | PEDRO AYALA |
| Zoning Plan Check | Cleared | 11/19/2025 | ELAHE MERRIKHI |
Contact Information
| Contractor | Vaisman Construction Inc; Lic. No.: 1076712-B | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/9/2026 | Partial Approval | DAKOTA LOW |
| BUILDING-Rough-Frame | 5/14/2026 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 5/14/2026 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 5/14/2026 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 5/14/2026 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 5/14/2026 | Corrections Issued | MORRIS JACKSON |
| Rough-Elec/Plmb/HVAC | 5/14/2026 | No Access for Inspection | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 5/14/2026 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 5/19/2026 | Corrections Issued | DAKOTA LOW |
| Shower Pan | 5/19/2026 | Not Ready for Inspection | DAKOTA LOW |
| Wood Frame | 5/19/2026 | Not Ready for Inspection | DAKOTA LOW |
| BUILDING-Rough-Frame | 5/21/2026 | Approved | DAKOTA LOW |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2026 | Approved | DAKOTA LOW |
| Green Building Rough | 5/21/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 5/21/2026 | Approved | DAKOTA LOW |
| PLUMBING-Rough | 5/21/2026 | Approved | DAKOTA LOW |
| Shower Pan | 5/21/2026 | Not Ready for Inspection | DAKOTA LOW |
| Verify Sprinkler Sign Off | 5/21/2026 | Approved | DAKOTA LOW |
| Insulation | 6/4/2026 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/4/2026 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 6/4/2026 | Approved | MORRIS JACKSON |
| Drywall Nailing | 6/10/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 6/10/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 6/12/2026 | Approved | DAKOTA LOW |