1475 N CAMPUS ROAD 90042

Certificate Information: 1475 N CAMPUS ROAD 90042

Application / Permit
25010-10000-03538
Plan Check / Job No.
B25LA32488
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New detached 2-story ADU
Permit Issued
Issued on 2/26/2026
Issuing Office
Current Status
Issued on 2/26/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/6/2025 APPLICANT
Assigned to Plan Check Engineer 8/14/2025 ARSALAN SHABESTARI
Corrections Issued 8/19/2025 ARSALAN SHABESTARI
Quality Review Completed 9/3/2025 GARO TELMI
Applicant returned to address corrections 11/1/2025 ARSALAN SHABESTARI
Plan Check Approved 12/9/2025 ARSALAN SHABESTARI
Issued 2/26/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/19/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 9/19/2025 MICHAEL BROWN
Sewer availability Cleared 9/19/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 10/15/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 11/1/2025 MICHAEL TEMPLE
GPI Written Notices Cleared 12/9/2025 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,
Engineer Hakobyan,, Sevak; Lic. No.: NA96829       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/2/2026 Partial Approval DAVID WILLIAMS
Pre-Inspection 3/10/2026 Partial Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 3/26/2026 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 3/26/2026 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/31/2026 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 4/2/2026 No Access for Inspection BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 4/6/2026 Approved DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 4/17/2026 Approved DAVID WILLIAMS
Deputy Wood Construction 5/27/2026 Conditional Approval NICHOLAS LOPEZ