Certificate Information: 7738 N BONNER AVE 91352

Application / Permit
25010-10000-03524
Plan Check / Job No.
B25LA32420
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ADU (1200 SF) PER CITY ORDINANCE AT REAR OF THE LOT.
Permit Issued
Issued on 10/2/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 FERNANDO FLORES
Corrections Issued 8/8/2025 FERNANDO FLORES
Building Plans Picked Up 8/13/2025 APPLICANT
Plan Check Approved 9/25/2025 DANIEL SMILEY
Issued 10/2/2025 APPLICANT
CofO in Progress 4/8/2026 MATTHEW NELSON
Permit Finaled 5/29/2026 RUBEN SALAS
CofO Issued 5/29/2026 RUBEN SALAS
Permit Finaled 5/29/2026 RUBEN SALAS

Permit Application Clearance Information

Clean Up Green Up Cleared 8/14/2025 ROSALINDA MEZA
Construction near power lines Cleared 8/18/2025 WALTER RAMIREZ
Construction within easement Cleared 8/18/2025 WALTER RAMIREZ
Address approval Cleared 8/21/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 8/21/2025 JESUS CISNEROS
Roof/Waste drainage to street Cleared 8/21/2025 JESUS CISNEROS
Sewer availability Cleared 8/21/2025 JESUS CISNEROS

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/12/2025 Approved MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 12/15/2025 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 12/17/2025 Approved MATTHEW NELSON
Footing/Foundation/Slab 12/17/2025 Approved MATTHEW NELSON
Wood Frame 1/9/2026 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 1/16/2026 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 1/16/2026 Corrections Issued MATTHEW NELSON
Green Building Rough 1/16/2026 Approved MATTHEW NELSON
HVAC-Rough 1/16/2026 Approved MATTHEW NELSON
PLUMBING-Rough 1/16/2026 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 1/16/2026 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/22/2026 Approved MATTHEW NELSON
ELECTRICAL-Rough 1/22/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/22/2026 Partial Approval MATTHEW NELSON
Insulation 1/26/2026 Approved MATTHEW NELSON
Drywall Nailing 1/29/2026 Approved MATTHEW NELSON
Shower Pan 1/29/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/3/2026 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 3/3/2026 Approved MATTHEW NELSON
ELECTRICAL-Final 4/1/2026 Corrections Issued MATTHEW NELSON
Final 4/1/2026 Corrections Issued MATTHEW NELSON
Green Building Final 4/1/2026 Approved MATTHEW NELSON
HVAC-Final 4/1/2026 Approved MATTHEW NELSON
PLUMBING-Final 4/1/2026 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 4/1/2026 Corrections Issued MATTHEW NELSON
Smoke Detectors 4/1/2026 Approved MATTHEW NELSON
ELECTRICAL-Final 4/8/2026 Approved MATTHEW NELSON
Final 4/8/2026 OK to Issue CofO MATTHEW NELSON
HVAC-Final 4/8/2026 Approved MATTHEW NELSON
PLUMBING-Final 4/8/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Approved MATTHEW NELSON
Service/Power Release 4/8/2026 Approved MATTHEW NELSON