7738 N BONNER AVE 91352
Certificate Information: 7738 N BONNER AVE 91352
- Application / Permit
- 25010-10000-03524
- Plan Check / Job No.
- B25LA32420
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY DETACHED ADU (1200 SF) PER CITY ORDINANCE AT REAR OF THE LOT.
- Permit Issued
- Issued on 10/2/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | FERNANDO FLORES |
| Corrections Issued | 8/8/2025 | FERNANDO FLORES |
| Building Plans Picked Up | 8/13/2025 | APPLICANT |
| Plan Check Approved | 9/25/2025 | DANIEL SMILEY |
| Issued | 10/2/2025 | APPLICANT |
| CofO in Progress | 4/8/2026 | MATTHEW NELSON |
| Permit Finaled | 5/29/2026 | RUBEN SALAS |
| CofO Issued | 5/29/2026 | RUBEN SALAS |
| Permit Finaled | 5/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 8/14/2025 | ROSALINDA MEZA |
| Construction near power lines | Cleared | 8/18/2025 | WALTER RAMIREZ |
| Construction within easement | Cleared | 8/18/2025 | WALTER RAMIREZ |
| Address approval | Cleared | 8/21/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2025 | JESUS CISNEROS |
| Roof/Waste drainage to street | Cleared | 8/21/2025 | JESUS CISNEROS |
| Sewer availability | Cleared | 8/21/2025 | JESUS CISNEROS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/12/2025 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 12/15/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/17/2025 | Approved | MATTHEW NELSON |
| Wood Frame | 1/9/2026 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/16/2026 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/16/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 1/16/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 1/16/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 1/16/2026 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 1/16/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/22/2026 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/22/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/22/2026 | Partial Approval | MATTHEW NELSON |
| Insulation | 1/26/2026 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/29/2026 | Approved | MATTHEW NELSON |
| Shower Pan | 1/29/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/3/2026 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/3/2026 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 4/1/2026 | Corrections Issued | MATTHEW NELSON |
| Final | 4/1/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 4/1/2026 | Approved | MATTHEW NELSON |
| HVAC-Final | 4/1/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 4/1/2026 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 4/1/2026 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 4/1/2026 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 4/8/2026 | Approved | MATTHEW NELSON |
| Final | 4/8/2026 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 4/8/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 4/8/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/8/2026 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 4/8/2026 | Approved | MATTHEW NELSON |