7810 1/4-3/4 S FLIGHT AVE 90045

Certificate Information: 7810 1/4-3/4 S FLIGHT AVE 90045

Application / Permit
25010-10000-03519
Plan Check / Job No.
B25LA32365
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New Detached 2-Story ADU (2-units) per GC 66323(a)(4)
Permit Issued
Issued on 10/22/2025
Issuing Office
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2025 APPLICANT
Assigned to Plan Check Engineer 8/14/2025 KHEDER ALRAZAA
Corrections Issued 8/19/2025 KHEDER ALRAZAA
Quality Review Completed 8/22/2025 PRANITA SHAH
Applicant returned to address corrections 9/10/2025 KHEDER ALRAZAA
Plan Check Approved 10/22/2025 KHEDER ALRAZAA
Issued 10/22/2025 APPLICANT
CofO in Progress 6/1/2026 MICHAEL LEWIS
Permit Finaled 6/2/2026 RICHARD STEINBACH
CofO Issued 6/2/2026 RICHARD STEINBACH
Permit Finaled 6/2/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/25/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 8/25/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/26/2025 JEANIE LAM
Sewer availability Cleared 8/26/2025 JEANIE LAM
Miscellaneous Cleared 9/2/2025 MICHAEL BROWN
Specific Plan Cleared 9/2/2025 HAMID GHAEMMAGHAMI
GPI Written Notices Cleared 9/11/2025 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 10/22/2025 KHEDER ALRAZAA

Contact Information

Contractor Owner-Builder       ,
Engineer Mniarji,, Majd Sameer; Lic. No.: C93049 7812 VASSAR AVENUE      CANOGA PARK, CA 91304

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/31/2025 Corrections Issued JESUS PINEDA
Sewer 10/31/2025 Not Ready for Inspection JESUS PINEDA
Sewer 11/1/2025 Partial Approval DAVID FEILER
Underground Mechanical 11/1/2025 Corrections Issued DAVID FEILER
Sewer 11/3/2025 Approved JESUS PINEDA
Underground Mechanical 11/3/2025 Not Ready for Inspection JESUS PINEDA
Grounding or Bonding 11/6/2025 Approved JESUS PINEDA
Underground Mechanical 11/6/2025 Approved JESUS PINEDA
Footing/Foundation/Slab 11/7/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 11/18/2025 Corrections Issued JESUS PINEDA
Excavation/Setback/Form/Re-Bar 11/24/2025 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 11/26/2025 Approved JESUS PINEDA
Deputy Wood Construction 12/4/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Corrections Issued JESUS PINEDA
Deputy Wood Construction 12/15/2025 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 12/23/2025 Approved JESUS PINEDA
PLUMBING-Rough 12/23/2025 Approved JESUS PINEDA
HVAC-Rough 1/2/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 1/7/2026 Corrections Issued JESUS PINEDA
Insulation 1/7/2026 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 1/9/2026 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 1/9/2026 Not Ready for Inspection ANTHONY EGSON
Insulation 1/9/2026 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 1/12/2026 Approved MICHAEL ALLEN
Insulation 1/12/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/12/2026 Partial Approval MICHAEL ALLEN
Drywall Nailing 1/20/2026 Approved JESUS PINEDA
Green Building Rough 1/20/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 2/5/2026 Partial Approval EUGENE CASSIDY
Shower Pan 2/5/2026 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 2/10/2026 Approved ANTHONY EGSON
Shower Pan 2/10/2026 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 2/13/2026 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 3/6/2026 Approved JESUS PINEDA
Service/Power Release 3/23/2026 Approved JESUS PINEDA
PLUMBING-Final 4/9/2026 Corrections Issued RUBEN RIVAS
PLUMBING-Final 4/15/2026 Approved JESUS PINEDA
Shower Pan 4/15/2026 Approved JESUS PINEDA
Final 5/11/2026 Corrections Issued MICHAEL LEWIS
Green Building Final 5/11/2026 Approved MICHAEL LEWIS
HVAC-Final 5/11/2026 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Not Required MICHAEL LEWIS
Smoke Detectors 5/11/2026 Corrections Issued MICHAEL LEWIS
Final 5/18/2026 Corrections Issued MICHAEL LEWIS
HVAC-Final 5/18/2026 Approved MICHAEL LEWIS
Smoke Detectors 5/18/2026 Approved MICHAEL LEWIS
Final 5/21/2026 Corrections Issued MICHAEL LEWIS
Final 5/29/2026 OK to Issue CofO MICHAEL LEWIS