400 N PINTORESCA DR 90272
Certificate Information: 400 N PINTORESCA DR 90272
- Application / Permit
- 25010-10000-03500
- Plan Check / Job No.
- B25LA32175
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND BASEMSENT.. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/15/2025
- Issuing Office
- Current Status
- Issued on 10/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2025 | KEVIN MORALES |
| Corrections Issued | 8/19/2025 | KEVIN MORALES |
| Quality Review Completed | 8/19/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/24/2025 | KEVIN MORALES |
| Plan Check Approved | 9/26/2025 | KEVIN MORALES |
| Issued | 10/15/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2025 | SAFA JAVANMARDI |
| Permit | Cleared | 8/19/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/19/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/19/2025 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 8/27/2025 | LAVEON RIDER |
Contact Information
| Architect | Bosio,, Michael Ryan; Lic. No.: NA40457 | , |
| Contractor | Clear Construction Inc; Lic. No.: 999874-B | , |
| Engineer | Piepers,, Forrest; Lic. No.: NA92425 | , |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/3/2025 | Partial Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 1/20/2026 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 1/28/2026 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 1/28/2026 | Permit Expired | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 1/29/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 3/11/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 3/27/2026 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 3/31/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/17/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/20/2026 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 4/30/2026 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 5/4/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 5/19/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 5/19/2026 | Partial Approval | MEL KHACHATOURIAN |