2031 S GLYNDON AVE 90291

Certificate Information: 2031 S GLYNDON AVE 90291

Application / Permit
25010-10000-03473
Plan Check / Job No.
B25LA31992
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 STORY SFD
Permit Issued
Issued on 11/20/2025
Issuing Office
Current Status
Issued on 11/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 HERNAN ARREOLA
Assigned to Zoning Architect 8/7/2025 SARHAD GHEVANDIAN
Corrections Issued 8/11/2025 HERNAN ARREOLA
Quality Review Completed 8/18/2025 GARO TELMI
Applicant returned to address corrections 9/26/2025 HERNAN ARREOLA
Plan Check Approved 10/6/2025 HERNAN ARREOLA
Plan Check Approved 10/6/2025 HERNAN ARREOLA
Issued 11/20/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 8/19/2025 RUEL COLE
Low Impact Development (LID) Cleared 8/26/2025 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 8/31/2025 CHRISTINE REUSCH
Roof/Waste drainage to street Cleared 8/31/2025 CHRISTINE REUSCH
Sewer availability Cleared 8/31/2025 CHRISTINE REUSCH
Specific Plan Cleared 9/15/2025 PEDRO AYALA
Zoning Plan Check Cleared 9/18/2025 SARHAD GHEVANDIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Engineer Yu,, Irene; Lic. No.: NA68382       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/25/2025 Approved RUBEN RIVAS
PLUMBING-Rough 11/25/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Partial Approval RUBEN RIVAS
Deputy Steel/Welding 12/10/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval RUBEN RIVAS
PLUMBING-Rough 1/9/2026 Approved WILBER ROSALES
Footing/Foundation/Slab 1/22/2026 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 1/28/2026 Corrections Issued RUBEN RIVAS
HVAC-Rough 1/28/2026 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Partial Approval RUBEN RIVAS
Deputy Wood Construction 2/19/2026 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 3/2/2026 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 3/2/2026 Approved MICHAEL ALLEN
Green Building Rough 3/2/2026 Partial Approval MICHAEL ALLEN
Verify Sprinkler Sign Off 3/2/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 3/4/2026 Corrections Issued RUBEN RIVAS
BUILDING-Rough-Frame 3/9/2026 Approved RUBEN RIVAS
Green Building Rough 3/9/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 3/9/2026 Partial Approval RUBEN RIVAS
Shower Pan 3/9/2026 Approved RUBEN RIVAS
Insulation 3/13/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 3/18/2026 Approved TEMISTOCLES CAAL
Drywall Nailing 3/23/2026 Approved RUBEN RIVAS
Service/Power Release 6/1/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Final 7/7/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Final 7/10/2026 Corrections Issued MICHAEL LEWIS
HVAC-Final 7/10/2026 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 7/16/2026 Not Ready for Inspection RUBEN RIVAS
HVAC-Final 7/16/2026 Corrections Issued RUBEN RIVAS
PLUMBING-Final 7/16/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Final 7/20/2026 Approved RUBEN RIVAS
Service/Power Release 7/20/2026 Approved RUBEN RIVAS