16641 W AKRON ST 90272
Certificate Information: 16641 W AKRON ST 90272
- Application / Permit
- 25010-10000-03454
- Plan Check / Job No.
- B25LA31837
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 3-STORY. NFPA 13D SPRINKLERS THROUGHOUT. EO8
- Permit Issued
- Issued on 12/12/2025
- Issuing Office
- Current Status
- Issued on 12/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2025 | JOE VO |
| Corrections Issued | 8/16/2025 | JOE VO |
| Quality Review Completed | 8/19/2025 | GARO TELMI |
| Applicant returned to address corrections | 12/2/2025 | JOE VO |
| Plan Check Approved | 12/9/2025 | JOE VO |
| Issued | 12/12/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2025 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 8/18/2025 | JOHN LIN |
| Sewer availability | Cleared | 8/18/2025 | JOHN LIN |
| Low Impact Development (LID) | Cleared | 8/27/2025 | ORVAL HERNANDEZ-MARCI |
| Hydrant and Access approval | Cleared | 9/3/2025 | JERRY KAO |
| GPI Written Notices | Cleared | 9/22/2025 | JOE VO |
| Trees in Parkway | Cleared | 10/22/2025 | RICHARD SANCHEZ |
| Coastal Zone | Cleared | 10/28/2025 | DALIA MOKAYED |
| Miscellaneous | Cleared | 10/28/2025 | DALIA MOKAYED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shirley,, Peter; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/13/2026 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 2/13/2026 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 2/20/2026 | Approved | BOBBY KEY |
| Pre-Inspection | 2/20/2026 | Partial Inspection | BOBBY KEY |
| Underground Mechanical | 3/3/2026 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 3/10/2026 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 3/12/2026 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 3/31/2026 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 4/24/2026 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 5/6/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 5/15/2026 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2026 | Corrections Issued | DANIEL VERA |
| PLUMBING-Rough | 5/18/2026 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Corrections Issued | DANIEL VERA |
| PLUMBING-Rough | 5/19/2026 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 6/5/2026 | No Result Entered | DANIEL VERA |
| Green Building Rough | 6/5/2026 | No Result Entered | DANIEL VERA |
| Verify Sprinkler Sign Off | 6/5/2026 | No Result Entered | DANIEL VERA |