11582 W SUNSET BLVD 90049
Certificate Information: 11582 W SUNSET BLVD 90049
- Application / Permit
- 25010-10000-03442
- Plan Check / Job No.
- B25LA31755
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New 2-story detached ADU PER CITY ORDINANCE WORK DONE PER ENGINEER DESIGN
- Permit Issued
- Issued on 2/5/2026
- Issuing Office
- Current Status
- Issued on 2/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2025 | KHUONG TRUONG |
| Corrections Issued | 8/15/2025 | KHUONG TRUONG |
| Quality Review Completed | 8/18/2025 | GARO TELMI |
| Plan Check Approved | 2/3/2026 | KHUONG TRUONG |
| Issued | 2/5/2026 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/1/2025 | RIDWAN HARDY |
| Address approval | Cleared | 11/5/2025 | CHRISTINE REUSCH |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2025 | CHRISTINE REUSCH |
| Roof/Waste drainage to street | Cleared | 11/5/2025 | CHRISTINE REUSCH |
| Sewer availability | Cleared | 11/5/2025 | CHRISTINE REUSCH |
| Specific Plan | Cleared | 11/5/2025 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 2/3/2026 | KHUONG TRUONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/16/2026 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 3/25/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/25/2026 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 4/8/2026 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 4/8/2026 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 4/8/2026 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 4/29/2026 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 4/29/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 4/29/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Partial Approval | EVAN COOPER |
| Green Building Rough | 5/11/2026 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 5/11/2026 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/1/2026 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | Corrections Issued | EVAN COOPER |