1272 N VAN NESS AVE 1-4 90038

Certificate Information: 1272 N VAN NESS AVE 1-4 90038

Application / Permit
25010-10000-03397
Plan Check / Job No.
B25LA30250
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: 4 NEW 2-STORY ADU PER CGS 66323.
Permit Issued
Issued on 1/15/2026
Issuing Office
Current Status
Issued on 1/15/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/22/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 VARAND SARKISIAN
Corrections Issued 7/29/2025 VARAND SARKISIAN
Quality Review Completed 7/30/2025 GARO TELMI
Applicant returned to address corrections 9/11/2025 VARAND SARKISIAN
Applicant returned to address corrections 9/12/2025 VARAND SARKISIAN
Plan Check Approved 1/15/2026 VARAND SARKISIAN
Issued 1/15/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/31/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/31/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 7/31/2025 RYAN CASTRO
Sewer availability Cleared 7/31/2025 RYAN CASTRO
Construction near power lines Cleared 9/25/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/22/2026 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 1/22/2026 No Access for Inspection CRAIG VAUGHAN
PLUMBING-Rough 1/22/2026 No Access for Inspection CRAIG VAUGHAN
Underground Mechanical 1/22/2026 No Access for Inspection CRAIG VAUGHAN
Pre-Inspection 2/26/2026 Partial Approval CRAIG VAUGHAN
Underground Mechanical 6/15/2026 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 6/25/2026 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/7/2026 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 7/9/2026 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 7/17/2026 Corrections Issued CRAIG VAUGHAN