10465 W ILONA AVE 90064

Certificate Information: 10465 W ILONA AVE 90064

Application / Permit
25010-10000-03393
Plan Check / Job No.
B25LA31258
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. New detached 2-story Accessory Dwelling Unit per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 12/5/2025
Issuing Office
Current Status
Issued on 12/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/29/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 ALEXANDER JOO
Corrections Issued 8/13/2025 ALEXANDER JOO
Quality Review Completed 8/15/2025 GARO TELMI
Applicant returned to address corrections 11/20/2025 ALEXANDER JOO
Plan Check Approved 12/2/2025 ALEXANDER JOO
Issued 12/5/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/27/2025 HISASHI KOBAYAKAWA
Specific Plan Cleared 9/8/2025 HAMID GHAEMMAGHAMI
Eng Process Fee Ord 176,300 Cleared 9/10/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/10/2025 HISASHI KOBAYAKAWA
Construction near power lines Cleared 11/1/2025 RIDWAN HARDY
Construction within easement Cleared 11/1/2025 RIDWAN HARDY
Roof/Waste drainage to street Cleared 11/4/2025 KIMBERLY HERNANDEZ
GPI Written Notices Cleared 11/20/2025 ALEXANDER JOO
Grading Pre-Inspection Cleared 11/20/2025 AL GAMBLE

Contact Information

Contractor Owner-Builder       ,
Engineer Taroian,, Armen; Lic. No.: C78011 411 PALM DR APT 204      GLENDALE, CA 91202

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/31/2025 Partial Approval RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 1/13/2026 Partial Approval MICHAEL ALLEN
Underground Mechanical 1/13/2026 Approved MICHAEL ALLEN
Deputy Other (see comments) 1/16/2026 Conditional Approval ANDREW NAVE
METHANE-Subgrade 1/16/2026 Approved DANIEL VERA
Footing/Foundation/Slab 1/27/2026 Not Ready for Inspection CARLOS MATAMOROS
METHANE-Barrier 1/27/2026 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/28/2026 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 3/11/2026 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Conditional Approval CARLOS MATAMOROS
Gas Test 3/11/2026 Approved CARLOS MATAMOROS
HVAC-Rough 3/11/2026 Approved CARLOS MATAMOROS
METHANE-Rough 3/11/2026 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/11/2026 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 3/11/2026 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 3/19/2026 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 3/19/2026 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/24/2026 Approved RYAN SALAZAR
Green Building Rough 3/24/2026 Approved RYAN SALAZAR
Wood Frame 3/24/2026 Approved RYAN SALAZAR
Insulation 3/27/2026 Corrections Issued CHRISTOPHER WILSON
Shower Pan 3/27/2026 Approved CHRISTOPHER WILSON
Final 4/1/2026 Corrections Issued CHRISTOPHER WILSON
Insulation 4/1/2026 Approved CHRISTOPHER WILSON
Drywall Nailing 4/7/2026 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 4/7/2026 Approved CARLOS MATAMOROS
Sewer 5/29/2026 Approved DAVID SCANTLIN
Underground Mechanical 5/29/2026 Approved DAVID SCANTLIN