654-656 N LAS LOMAS AVE 90272
Certificate Information: 654-656 N LAS LOMAS AVE 90272
- Application / Permit
- 25010-10000-03379
- Plan Check / Job No.
- B25LA31198
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2025 WILDFIRE REBUILD, TWO-FAMILY DWELLING . NFPA 13D SPRINKLERS THROUGHOUT (Built Per 1928LA17828)
- Permit Issued
- Issued on 12/1/2025
- Issuing Office
- Current Status
- Issued on 12/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | MANUEL MONTUFAR |
| Corrections Issued | 8/11/2025 | MANUEL MONTUFAR |
| Quality Review Completed | 8/12/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/10/2025 | MANUEL MONTUFAR |
| Plan Check Approved | 9/16/2025 | MANUEL MONTUFAR |
| Issued | 12/1/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2025 | MICHAEL BROWN |
| Permit | Cleared | 8/11/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 8/11/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 8/11/2025 | MICHAEL BROWN |
| Address approval | Cleared | 8/13/2025 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 9/8/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 9/10/2025 | PATRICK PEREZ |
Contact Information
| Contractor | Arttcon Inc; Lic. No.: 1138192-B | , |
| Engineer | Farag,, Amgad N; Lic. No.: C74076 | 27050 MAPLE TREE CT VALENCIA, CA 91381 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2026 | Corrections Issued | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 1/30/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 1/30/2026 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 1/30/2026 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 2/9/2026 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 2/9/2026 | Approved | MICHAEL ALLEN |
| Grounding or Bonding | 2/9/2026 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2026 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Corrections Issued | DANIEL VERA |
| PLUMBING-Rough | 4/7/2026 | Not Ready for Inspection | DANIEL VERA |