15273 W DE PAUW ST 90272

Certificate Information: 15273 W DE PAUW ST 90272

Application / Permit
25010-10000-03375
Plan Check / Job No.
B25LA31194
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/20/2025
Issuing Office
Current Status
Issued on 10/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/30/2025 APPLICANT
Assigned to Plan Check Engineer 7/31/2025 JOE VO
Corrections Issued 8/3/2025 JOE VO
Quality Review Completed 8/7/2025 GARO TELMI
Plan Check Approved 10/14/2025 JOE VO
Issued 10/20/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/7/2025 CINDY QI
Permit Cleared 8/7/2025 CINDY QI
Roof/Waste drainage to street Cleared 8/7/2025 CINDY QI
Sewer availability Cleared 8/7/2025 CINDY QI
Low Impact Development (LID) Cleared 9/19/2025 ERNEST TSE
Hydrant and Access approval Cleared 9/22/2025 KURT CORRAL
GPI Written Notices Cleared 10/14/2025 JOE VO

Contact Information

Architect Bosio,, Michael Ryan; Lic. No.: NA40457       ,
Contractor Clear Construction Inc; Lic. No.: 999874-B       ,
Engineer Piepers,, Forrest; Lic. No.: NA92425       ,

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/12/2026 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 5/15/2026 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 5/19/2026 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 5/21/2026 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 5/21/2026 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 6/2/2026 Partial Approval EVAN COOPER
PLUMBING-Rough 6/2/2026 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/29/2026 Not Ready for Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 6/29/2026 Not Ready for Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 7/7/2026 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 7/16/2026 Not Ready for Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 7/17/2026 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/23/2026 Partial Approval STEPHANIE SWANSON