427 N WYNOLA ST 90272

Certificate Information: 427 N WYNOLA ST 90272

Application / Permit
25010-10000-03372
Plan Check / Job No.
B25LA31190
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/15/2025
Issuing Office
Current Status
Issued on 10/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/8/2025 APPLICANT
Assigned to Plan Check Engineer 8/14/2025 KEVIN MORALES
Corrections Issued 8/19/2025 KEVIN MORALES
Quality Review Completed 8/19/2025 EUGENE BARBEAU
Applicant returned to address corrections 9/22/2025 KEVIN MORALES
Plan Check Approved 10/2/2025 KEVIN MORALES
Issued 10/15/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/19/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/19/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 8/19/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/19/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 9/25/2025 JERRY KAO

Contact Information

Contractor Majestic Horizon Builders Inc; Lic. No.: 542977-B       ,

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/18/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 1/20/2026 Approved MEL KHACHATOURIAN
Deputy Reinf. Concrete 1/22/2026 Conditional Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 2/5/2026 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Partial Approval MICHAEL ALLEN
Sewer 3/11/2026 Approved EVAN COOPER
Underground Mechanical 3/12/2026 Partial Approval MEL KHACHATOURIAN
Deputy Drilled-In Anchors 3/23/2026 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 3/25/2026 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Partial Approval MEL KHACHATOURIAN
HVAC-Rough 3/27/2026 Approved MEL KHACHATOURIAN
PLUMBING-Rough 4/15/2026 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 4/24/2026 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 4/30/2026 Partial Approval MEL KHACHATOURIAN
Wood Frame 4/30/2026 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/4/2026 Approved MEL KHACHATOURIAN
Green Building Rough 5/4/2026 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 5/4/2026 Approved MEL KHACHATOURIAN
Wood Frame 5/4/2026 Approved MEL KHACHATOURIAN
Insulation 5/8/2026 Approved BOBBY KEY
Drywall Nailing 5/18/2026 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 5/18/2026 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 6/30/2026 Partial Approval RYAN SALAZAR
Shower Pan 6/30/2026 Approved RYAN SALAZAR
Underground Mechanical 7/14/2026 No Access for Inspection MEL KHACHATOURIAN
Underground Mechanical 7/15/2026 No Access for Inspection MEL KHACHATOURIAN
Underground Mechanical 7/16/2026 Partial Approval MEL KHACHATOURIAN