2106 W CLIFFORD ST 90026
Certificate Information: 2106 W CLIFFORD ST 90026
- Application / Permit
- 25010-10000-03325
- Plan Check / Job No.
- B25LA30823
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: NEW DETACHED 1 STORY ADU PER PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 2/18/2026
- Issuing Office
- Current Status
- Issued on 2/18/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | KHEDER ALRAZAA |
| Corrections Issued | 8/14/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 8/15/2025 | GARO TELMI |
| Applicant returned to address corrections | 10/31/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 11/21/2025 | KHEDER ALRAZAA |
| Issued | 2/18/2026 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/14/2025 | KHEDER ALRAZAA |
| Grading Pre-Inspection | Cleared | 8/14/2025 | KHEDER ALRAZAA |
| Address approval | Cleared | 8/22/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 9/2/2025 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 9/4/2025 | FRANK GOMEZ |
| Roof/Waste drainage to street | Cleared | 9/9/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Buildoly Inc; Lic. No.: 1134744-B | , |
| Engineer | Dweab,, Shadi; Lic. No.: C91184 | 16760 GREEN TREE BLVD APT #17 VICTORVILLE, CA 92395 |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/26/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 3/26/2026 | Partial Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 4/15/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 4/20/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/23/2026 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 5/20/2026 | Conditional Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/18/2026 | No Result Entered | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/18/2026 | No Result Entered | HAMIK HARTOUNIAN |