918 N FISKE ST 90272
Certificate Information: 918 N FISKE ST 90272
- Application / Permit
- 25010-10000-03299
- Plan Check / Job No.
- B25LA30616
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. INELIGIBLE
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Current Status
- Issued on 11/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | VIVIAN LAO |
| Corrections Issued | 8/26/2025 | VIVIAN LAO |
| Quality Review Completed | 8/26/2025 | JOHN FRANCIA |
| Applicant returned to address corrections | 9/24/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 9/25/2025 | VIVIAN LAO |
| Plan Check Approved | 10/14/2025 | VIVIAN LAO |
| Issued | 11/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/25/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/26/2025 | ABEL CASILLAS |
| Hydrant and Access approval | Cleared | 8/29/2025 | LAVEON RIDER |
Contact Information
| Contractor | Ariel Construction Inc A California Corporation; Lic. No.: 861664-B | , |
| Engineer | Kashe,, Andrew; Lic. No.: NA94117 | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/16/2025 | Partial Approval | TEMISTOCLES CAAL |
| Pre-Inspection | 12/16/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/10/2026 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 2/13/2026 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2026 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 3/4/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Rough | 3/6/2026 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Not Ready for Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 5/26/2026 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | Not Ready for Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 6/1/2026 | Approved | JESUS PINEDA |