5641 E BERKSHIRE DR 90032
Certificate Information: 5641 E BERKSHIRE DR 90032
- Application / Permit
- 25010-10000-03294
- Plan Check / Job No.
- B25LA30597
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached 2 story ADU with roof deck and balcony per LAMC 12.22A 33(b)(1).
- Permit Issued
- Issued on 4/16/2026
- Issuing Office
- Current Status
- Issued on 4/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | MARCELA FRANQUEZ |
| Corrections Issued | 8/19/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 8/20/2025 | TU HUA |
| Applicant returned to address corrections | 11/17/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 4/15/2026 | MARCELA FRANQUEZ |
| Issued | 4/16/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 8/29/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2025 | TAL SHEMEN |
| CPC | Cleared | 9/4/2025 | YINGSHI HUANG |
| Sewer availability | Cleared | 9/8/2025 | TAL SHEMEN |
| City Hist. Cultural Monument | Cleared | 10/20/2025 | DAMIAN GATTO |
| HPOZ | Cleared | 10/20/2025 | DAMIAN GATTO |
| GPI Written Notices | Cleared | 11/18/2025 | MARCELA FRANQUEZ |
| Grading Pre-Inspection | Cleared | 11/18/2025 | MARCELA FRANQUEZ |
| Disturb/Remove Protected Trees | Cleared | 3/23/2026 | MIGUEL ORNELAS |
Contact Information
| Architect | Wang,, Yang; Lic. No.: C35954 | 216 W. GARVEY AVENUE_UNIT D MONTEREY PARK, CA 91754 |
| Contractor | Potato Construction Inc; Lic. No.: 1003152-B | , |
| Engineer | Gao,, Jianfeng; Lic. No.: C88478 | 18825 ELMHURST ST ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/15/2026 | Partial Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 5/21/2026 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/21/2026 | Approved | LILIANA PORTILLO |