725 N JACON WAY 90272

Certificate Information: 725 N JACON WAY 90272

Application / Permit
25010-10000-03293
Plan Check / Job No.
B25LA30594
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
Permit Issued
Issued on 10/23/2025
Issuing Office
Current Status
Issued on 10/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/30/2025 APPLICANT
Assigned to Plan Check Engineer 7/31/2025 HERNAN ARREOLA
Corrections Issued 8/8/2025 HERNAN ARREOLA
Quality Review Completed 8/14/2025 GARO TELMI
Applicant returned to address corrections 9/4/2025 HERNAN ARREOLA
Applicant returned to address corrections 10/3/2025 HERNAN ARREOLA
Plan Check Approved 10/23/2025 HERNAN ARREOLA
Issued 10/23/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/8/2025 DAVID VO
Sewer availability Cleared 8/8/2025 DAVID VO
Hydrant and Access approval Cleared 9/10/2025 JOHN CONNEALLY
Low Impact Development (LID) Cleared 9/10/2025 ERNEST TSE
Construction near power lines Cleared 10/4/2025 RIDWAN HARDY

Contact Information

Contractor Classical Progression Inc; Lic. No.: 823135-B       ,
Engineer Barr,, Joseph Daniel; Lic. No.: C70708 1185 HERITAGE FARM RD      HICKORY, NC 28601
Engineer Khanlou,, Amir; Lic. No.: NA87550       ,

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/20/2025 Partial Inspection BOBBY KEY
Deputy Other (see comments) 1/20/2026 Conditional Approval BOBBY KEY
Deputy Reinf. Concrete 1/20/2026 Conditional Approval BOBBY KEY
PLUMBING-Rough 1/21/2026 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 2/2/2026 Not Ready for Inspection DANIEL VERA
Deputy Reinf. Concrete 2/3/2026 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 2/5/2026 Approved BOBBY KEY
Excavation/Setback/Form/Re-Bar 2/5/2026 Partial Approval BOBBY KEY
Deputy Reinf. Concrete 2/6/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/10/2026 Approved MEL KHACHATOURIAN
Deputy Reinf. Concrete 2/20/2026 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/20/2026 Corrections Issued DANIEL VERA
Deputy Wood Construction 3/23/2026 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 4/27/2026 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/27/2026 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/8/2026 Approved MICHAEL ALLEN