725 N JACON WAY 90272
Certificate Information: 725 N JACON WAY 90272
- Application / Permit
- 25010-10000-03293
- Plan Check / Job No.
- B25LA30594
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 10/23/2025
- Issuing Office
- Current Status
- Issued on 10/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2025 | HERNAN ARREOLA |
| Corrections Issued | 8/8/2025 | HERNAN ARREOLA |
| Quality Review Completed | 8/14/2025 | GARO TELMI |
| Applicant returned to address corrections | 9/4/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/3/2025 | HERNAN ARREOLA |
| Plan Check Approved | 10/23/2025 | HERNAN ARREOLA |
| Issued | 10/23/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2025 | DAVID VO |
| Sewer availability | Cleared | 8/8/2025 | DAVID VO |
| Hydrant and Access approval | Cleared | 9/10/2025 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 9/10/2025 | ERNEST TSE |
| Construction near power lines | Cleared | 10/4/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Classical Progression Inc; Lic. No.: 823135-B | , |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Khanlou,, Amir; Lic. No.: NA87550 | , |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/20/2025 | Partial Inspection | BOBBY KEY |
| Deputy Other (see comments) | 1/20/2026 | Conditional Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 1/20/2026 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 1/21/2026 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 2/2/2026 | Not Ready for Inspection | DANIEL VERA |
| Deputy Reinf. Concrete | 2/3/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 2/5/2026 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 2/5/2026 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 2/6/2026 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 2/10/2026 | Approved | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 2/20/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Corrections Issued | DANIEL VERA |
| Deputy Wood Construction | 3/23/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 4/27/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2026 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2026 | Approved | MICHAEL ALLEN |